Data center campus · Texas 170 and Park Vista Boulevard, AllianceTexas, north Fort Worth, Tarrant County, Texas
Meta Fort Worth data center
Operating
as of Nov. 17, 2020
Meta's data center campus in the AllianceTexas development in north Fort Worth, first opened in 2017 and planned in 2016 to grow to five buildings.
PowerNot statedNot reported in the records found
Floor area2,500,000sq ft
Site150acres
Who is behind it
ProjectMeta Fort Worth data center
Developer and teamMeta
End userNot found in the recordsNot yet named in any record or credited report we have found.
The record, newest first
The Dallas Morning News reported new state filings for a $25 million renovation on the 150-acre campus, whose first phase opened in 2017. (The Dallas Morning News, Nov. 17, 2020)
Facebook said it would grow the campus to five buildings and about 2.5 million square feet, with investment possibly above $1 billion. (Dallas Innovates, Nov. 16, 2016)
Facebook bought about 39 acres next to its 110-acre Alliance site, where construction began in July 2015. (Dallas Innovates, Feb. 18, 2016)
Conflicts and open questions
- The Dallas Morning News page showed no date; the date is taken from its URL.
- No recent primary record was opened; sqft is the 2016 planned figure.
The full record
- Evidence
- News reports; primary records not yet obtained
- Size class