Data center campus · outside Hubbard, Hill County, Texas

Nexus Data Centers Hubbard campus

Under construction as of Aug. 20, 2026

A gas-powered, multi-building AI campus on roughly 2,000 to 3,000 acres outside Hubbard, financed in 2026 with Anthropic reported as its main tenant. Also known as: Nexus Apex, Apex DFW HB1, Apex HB2.

Cite← Texas data centers
Anderson CountyAndrews CountyAngelina CountyAransas CountyArcher CountyArmstrong CountyAtascosa CountyAustin CountyBailey CountyBandera CountyBastrop CountyBaylor CountyBee CountyBell CountyBexar CountyBlanco CountyBorden CountyBosque CountyBowie CountyBrazoria CountyBrazos CountyBrewster CountyBriscoe CountyBrooks CountyBrown CountyBurleson CountyBurnet CountyCaldwell CountyCalhoun CountyCallahan CountyCameron CountyCamp CountyCarson CountyCass CountyCastro CountyChambers CountyCherokee CountyChildress CountyClay CountyCochran CountyCoke CountyColeman CountyCollin CountyCollingsworth CountyColorado CountyComal CountyComanche CountyConcho CountyCooke CountyCoryell CountyCottle CountyCrane CountyCrockett CountyCrosby CountyCulberson CountyDallam CountyDallas CountyDawson CountyDeaf Smith CountyDelta CountyDenton CountyDeWitt CountyDickens CountyDimmit CountyDonley CountyDuval CountyEastland CountyEctor CountyEdwards CountyEl Paso CountyEllis CountyErath CountyFalls CountyFannin CountyFayette CountyFisher CountyFloyd CountyFoard CountyFort Bend CountyFranklin CountyFreestone CountyFrio CountyGaines CountyGalveston CountyGarza CountyGillespie CountyGlasscock CountyGoliad CountyGonzales CountyGray CountyGrayson CountyGregg CountyGrimes CountyGuadalupe CountyHale CountyHall CountyHamilton CountyHansford CountyHardeman CountyHardin CountyHarris CountyHarrison CountyHartley CountyHaskell CountyHays CountyHemphill CountyHenderson CountyHidalgo CountyHill CountyHockley CountyHood CountyHopkins CountyHouston CountyHoward CountyHudspeth CountyHunt CountyHutchinson CountyIrion CountyJack CountyJackson CountyJasper CountyJeff Davis CountyJefferson CountyJim Hogg CountyJim Wells CountyJohnson CountyJones CountyKarnes CountyKaufman CountyKendall CountyKenedy CountyKent CountyKerr CountyKimble CountyKing CountyKinney CountyKleberg CountyKnox CountyLa Salle CountyLamar CountyLamb CountyLampasas CountyLavaca CountyLee CountyLeon CountyLiberty CountyLimestone CountyLipscomb CountyLive Oak CountyLlano CountyLoving CountyLubbock CountyLynn CountyMadison CountyMarion CountyMartin CountyMason CountyMatagorda CountyMaverick CountyMcCulloch CountyMcLennan CountyMcMullen CountyMedina CountyMenard CountyMidland CountyMilam CountyMills CountyMitchell CountyMontague CountyMontgomery CountyMoore CountyMorris CountyMotley CountyNacogdoches CountyNavarro CountyNewton CountyNolan CountyNueces CountyOchiltree CountyOldham CountyOrange CountyPalo Pinto CountyPanola CountyParker CountyParmer CountyPecos CountyPolk CountyPotter CountyPresidio CountyRains CountyRandall CountyReagan CountyReal CountyRed River CountyReeves CountyRefugio CountyRoberts CountyRobertson CountyRockwall CountyRunnels CountyRusk CountySabine CountySan Augustine CountySan Jacinto CountySan Patricio CountySan Saba CountySchleicher CountyScurry CountyShackelford CountyShelby CountySherman CountySmith CountySomervell CountyStarr CountyStephens CountySterling CountyStonewall CountySutton CountySwisher CountyTarrant CountyTaylor CountyTerrell CountyTerry CountyThrockmorton CountyTitus CountyTom Green CountyTravis CountyTrinity CountyTyler CountyUpshur CountyUpton CountyUvalde CountyVal Verde CountyVan Zandt CountyVictoria CountyWalker CountyWaller CountyWard CountyWashington CountyWebb CountyWharton CountyWheeler CountyWichita CountyWilbarger CountyWillacy CountyWilliamson CountyWilson CountyWinkler CountyWise CountyWood CountyYoakum CountyYoung CountyZapata CountyZavala CountyNexus Data Centers Hubbard campus · Under construction · 600 MW
Power600MW reported · stated

Who is behind it

ProjectNexus Data Centers Hubbard campusAlso: Nexus Apex, Apex DFW HB1, Apex HB2
Developer and teamNexus Data Centers
End userAnthropic (reported)

The record, newest first

  1. Trade press reported a roughly $1.3 billion mezzanine loan that completed a $16 billion financing for phase one, with Google guaranteeing the senior debt and Anthropic reported as the primary tenant. (The Next Web, Aug. 20, 2026; W.Media, Aug. 20, 2026)

  2. A second building of the same size and cost (Apex HB2) was registered, with work listed from June 2026 to January 2028. (Texas Department of Licensing and Regulation, June 25, 2026)

  3. Nexus Data Centers Hubbard LLC registered its first building (Apex DFW HB1, about 491,000 sq ft, $400 million) with the state licensing agency, listing a January 2026 start and October 2027 finish. (Texas Department of Licensing and Regulation, June 11, 2026)

  4. Hill County adopted a one-year moratorium on new data centers that exempts projects already under construction; the Nexus site near Hubbard was described as already being built. (The Lakelander, May 21, 2026)

  5. The county judge announced that Nexus had left abatement negotiations and would not ask the county for a tax break; the project continued, and the company had reported buying about 3,000 acres. (KXXV, April 7, 2026; The Lakelander, April 17, 2026)

  6. After a public hearing, Hill County commissioners approved a reinvestment zone for the Nexus site, a first step toward any abatement; the plan was described as four 400,000 sq ft data center buildings plus a power plant that has TCEQ permits. (The Lakelander, Feb. 19, 2026)

Conflicts and open questions

  • Acreage differs by source: about 2,000 acres (The Lakelander), 2,900 acres (trade press on the financing), and about 3,000 acres (KXXV, citing what Nexus told the county).
  • Anthropic as tenant and Google's guarantee come from reporting attributed to Bloomberg and unnamed sources, not from a company statement we opened.
  • No record we opened links this campus to Project Aquila (RCM Hill LLC), the separate Hill County land deal behind the moratorium lawsuit.
  • Gas plant generating capacity was not stated in sources we opened.

The full record

Status note
Site work has been reported since late 2025; Nexus reached a final investment decision on phase one in August 2026.
Power note
Trade press describes the campus as up to 600 MW.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.