Data center campus · Ward County (exact location not reported), Ward County, Texas

Nscale Ward County campus (Ionic Digital Cedarvale site)

Under construction as of July 20, 2026

A former bitcoin mining site in Ward County that Ionic Digital has leased to Nscale for GPU capacity serving Microsoft. Also known as: Cedarvale.

Cite← Texas data centers
Anderson CountyAndrews CountyAngelina CountyAransas CountyArcher CountyArmstrong CountyAtascosa CountyAustin CountyBailey CountyBandera CountyBastrop CountyBaylor CountyBee CountyBell CountyBexar CountyBlanco CountyBorden CountyBosque CountyBowie CountyBrazoria CountyBrazos CountyBrewster CountyBriscoe CountyBrooks CountyBrown CountyBurleson CountyBurnet CountyCaldwell CountyCalhoun CountyCallahan CountyCameron CountyCamp CountyCarson CountyCass CountyCastro CountyChambers CountyCherokee CountyChildress CountyClay CountyCochran CountyCoke CountyColeman CountyCollin CountyCollingsworth CountyColorado CountyComal CountyComanche CountyConcho CountyCooke CountyCoryell CountyCottle CountyCrane CountyCrockett CountyCrosby CountyCulberson CountyDallam CountyDallas CountyDawson CountyDeaf Smith CountyDelta CountyDenton CountyDeWitt CountyDickens CountyDimmit CountyDonley CountyDuval CountyEastland CountyEctor CountyEdwards CountyEl Paso CountyEllis CountyErath CountyFalls CountyFannin CountyFayette CountyFisher CountyFloyd CountyFoard CountyFort Bend CountyFranklin CountyFreestone CountyFrio CountyGaines CountyGalveston CountyGarza CountyGillespie CountyGlasscock CountyGoliad CountyGonzales CountyGray CountyGrayson CountyGregg CountyGrimes CountyGuadalupe CountyHale CountyHall CountyHamilton CountyHansford CountyHardeman CountyHardin CountyHarris CountyHarrison CountyHartley CountyHaskell CountyHays CountyHemphill CountyHenderson CountyHidalgo CountyHill CountyHockley CountyHood CountyHopkins CountyHouston CountyHoward CountyHudspeth CountyHunt CountyHutchinson CountyIrion CountyJack CountyJackson CountyJasper CountyJeff Davis CountyJefferson CountyJim Hogg CountyJim Wells CountyJohnson CountyJones CountyKarnes CountyKaufman CountyKendall CountyKenedy CountyKent CountyKerr CountyKimble CountyKing CountyKinney CountyKleberg CountyKnox CountyLa Salle CountyLamar CountyLamb CountyLampasas CountyLavaca CountyLee CountyLeon CountyLiberty CountyLimestone CountyLipscomb CountyLive Oak CountyLlano CountyLoving CountyLubbock CountyLynn CountyMadison CountyMarion CountyMartin CountyMason CountyMatagorda CountyMaverick CountyMcCulloch CountyMcLennan CountyMcMullen CountyMedina CountyMenard CountyMidland CountyMilam CountyMills CountyMitchell CountyMontague CountyMontgomery CountyMoore CountyMorris CountyMotley CountyNacogdoches CountyNavarro CountyNewton CountyNolan CountyNueces CountyOchiltree CountyOldham CountyOrange CountyPalo Pinto CountyPanola CountyParker CountyParmer CountyPecos CountyPolk CountyPotter CountyPresidio CountyRains CountyRandall CountyReagan CountyReal CountyRed River CountyReeves CountyRefugio CountyRoberts CountyRobertson CountyRockwall CountyRunnels CountyRusk CountySabine CountySan Augustine CountySan Jacinto CountySan Patricio CountySan Saba CountySchleicher CountyScurry CountyShackelford CountyShelby CountySherman CountySmith CountySomervell CountyStarr CountyStephens CountySterling CountyStonewall CountySutton CountySwisher CountyTarrant CountyTaylor CountyTerrell CountyTerry CountyThrockmorton CountyTitus CountyTom Green CountyTravis CountyTrinity CountyTyler CountyUpshur CountyUpton CountyUvalde CountyVal Verde CountyVan Zandt CountyVictoria CountyWalker CountyWaller CountyWard CountyWashington CountyWebb CountyWharton CountyWheeler CountyWichita CountyWilbarger CountyWillacy CountyWilliamson CountyWilson CountyWinkler CountyWise CountyWood CountyYoakum CountyYoung CountyZapata CountyZavala CountyNscale Ward County campus (Ionic Digital Cedarvale site) · Under construction · 234 MW
Power234MW reported · record
Site136acres

Who is behind it

ProjectNscale Ward County campus (Ionic Digital Cedarvale site)Also: Cedarvale
Developer and teamIonic Digital
End userMicrosoft

The record, newest first

  1. Ionic's IPO prospectus said 89 MW more is expected in the second half of 2027 and that it is seeking up to about 700 MW, depending on two utility projects. (U.S. Securities and Exchange Commission, July 20, 2026)

  2. All bitcoin mining equipment at the site had been decommissioned by this date. (U.S. Securities and Exchange Commission, July 20, 2026)

  3. Ionic Digital and Nscale announced a 10-year lease of the entire 234 MW Cedarvale facility, with Nscale planning about 104,000 Nvidia GB300 GPUs for Microsoft. (KSST Radio, Oct. 15, 2025)

Conflicts and open questions

  • Nscale leases about 50 acres; Ionic is developing the remaining 86 acres (acres field sums both).
  • Coordinates are a county-level approximation; no address or town was reported.
  • Microsoft as end user comes from the October 2025 lease announcement coverage; the prospectus mentions Microsoft only as holding an option on added power.

The full record

Status note
Mining equipment was decommissioned in December 2025; Ionic says development of the rest of the property has begun and monthly lease payments start in August 2026.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)