Data center campus · northwest corner of Sunrise Road and Belt Line Road, Lancaster, Dallas County, Texas
NTT Lancaster campus (TX10)
Approved
as of Dec. 2024
An NTT data center campus on about 109 acres in Lancaster backed by a city economic development agreement. Also known as: TX10.
PowerNot statedNot reported in the records found
Floor area225,000sq ft
Site108.652acres
Who is behind it
ProjectNTT Lancaster campus (TX10)Also: TX10
Developer and teamNTT Global Data Centers
End userNot found in the recordsNot yet named in any record or credited report we have found.
The record, newest first
Lancaster City Council approved a Chapter 380 agreement for an NTT data center of at least 225,000 square feet on about 108.7 acres, with occupancy required by Jan. 1, 2028. (Focus Daily News, Dec. 26, 2024)
Conflicts and open questions
- Exact council vote date not given ('earlier this month' in a Dec. 26, 2024 article).
- No MW figure found.
The full record
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)