QTS Irving campus (DFW1)
A 56-acre QTS campus on Longhorn Drive in Irving that has grown from two original buildings to six, with more than 165 MW of critical capacity. Also known as: Irving 1, DFW1.
Who is behind it
The record, newest first
QTS's location page described a six-building master-planned campus on 56 acres with more than 165 MW of critical capacity. (QTS Data Centers, Sept. 9, 2026)
QTS Irving DC6, LLC registered an $8 million project to enclose four buildings into one secured campus, running November 2025 to August 2026. (Texas Department of Licensing and Regulation, Oct. 10, 2025)
QTS registered a $152 million, 210,755 sq ft two-story phased data center at 6300 Longhorn Drive, scheduled for August 2024 to November 2025. (Texas Department of Licensing and Regulation, March 24, 2024)
QTS registered a two-story, 214,800 sq ft core-and-shell building (DFW1-DC4), estimated at $65 million, for May 2023 to September 2024. (Texas Department of Licensing and Regulation, Dec. 14, 2022)
Trade press reported plans for a fifth building, DC5: a $180 million, 337,190 sq ft data center at 6300 Longhorn Drive, next to a campus then put at 55 acres and 147 MW. (DatacenterDynamics, Oct. 4, 2022)
Conflicts and open questions
- Building names conflict: QTS's page puts DC5 at 6300 and DC6 at 6440 Longhorn Drive, while the 2024 TDLR filing at 6300 Longhorn is titled DFW1-DC6.
- The DC4 TDLR filing lists the address as '3 Longhorn Dr.'; QTS lists DC4 at 6311 Longhorn Drive.
- Earlier reporting (2022) gave the campus as 55 acres and 147 MW; QTS now states 56 acres and 165+ MW.
- Coordinates are approximate, from the Longhorn Drive addresses.
The full record
- Status note
- QTS lists six buildings on the campus; the page does not say which are all in service.
- Power note
- QTS states 165+ MW of critical campus capacity.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)