Data center campus · Former bottle plant on Fidelity Street, Jacinto City, Harris County, Texas

Raeden Jacinto City data center

Proposed as of Sept. 11, 2026

Raeden proposes converting a vacant 30-acre former glass bottle plant on Fidelity Street in Jacinto City into a 50 MW AI inference data center, over the city council's stated opposition. Also known as: Houston Hyperscale (site marketing name).

Cite← Texas data centers
Anderson CountyAndrews CountyAngelina CountyAransas CountyArcher CountyArmstrong CountyAtascosa CountyAustin CountyBailey CountyBandera CountyBastrop CountyBaylor CountyBee CountyBell CountyBexar CountyBlanco CountyBorden CountyBosque CountyBowie CountyBrazoria CountyBrazos CountyBrewster CountyBriscoe CountyBrooks CountyBrown CountyBurleson CountyBurnet CountyCaldwell CountyCalhoun CountyCallahan CountyCameron CountyCamp CountyCarson CountyCass CountyCastro CountyChambers CountyCherokee CountyChildress CountyClay CountyCochran CountyCoke CountyColeman CountyCollin CountyCollingsworth CountyColorado CountyComal CountyComanche CountyConcho CountyCooke CountyCoryell CountyCottle CountyCrane CountyCrockett CountyCrosby CountyCulberson CountyDallam CountyDallas CountyDawson CountyDeaf Smith CountyDelta CountyDenton CountyDeWitt CountyDickens CountyDimmit CountyDonley CountyDuval CountyEastland CountyEctor CountyEdwards CountyEl Paso CountyEllis CountyErath CountyFalls CountyFannin CountyFayette CountyFisher CountyFloyd CountyFoard CountyFort Bend CountyFranklin CountyFreestone CountyFrio CountyGaines CountyGalveston CountyGarza CountyGillespie CountyGlasscock CountyGoliad CountyGonzales CountyGray CountyGrayson CountyGregg CountyGrimes CountyGuadalupe CountyHale CountyHall CountyHamilton CountyHansford CountyHardeman CountyHardin CountyHarris CountyHarrison CountyHartley CountyHaskell CountyHays CountyHemphill CountyHenderson CountyHidalgo CountyHill CountyHockley CountyHood CountyHopkins CountyHouston CountyHoward CountyHudspeth CountyHunt CountyHutchinson CountyIrion CountyJack CountyJackson CountyJasper CountyJeff Davis CountyJefferson CountyJim Hogg CountyJim Wells CountyJohnson CountyJones CountyKarnes CountyKaufman CountyKendall CountyKenedy CountyKent CountyKerr CountyKimble CountyKing CountyKinney CountyKleberg CountyKnox CountyLa Salle CountyLamar CountyLamb CountyLampasas CountyLavaca CountyLee CountyLeon CountyLiberty CountyLimestone CountyLipscomb CountyLive Oak CountyLlano CountyLoving CountyLubbock CountyLynn CountyMadison CountyMarion CountyMartin CountyMason CountyMatagorda CountyMaverick CountyMcCulloch CountyMcLennan CountyMcMullen CountyMedina CountyMenard CountyMidland CountyMilam CountyMills CountyMitchell CountyMontague CountyMontgomery CountyMoore CountyMorris CountyMotley CountyNacogdoches CountyNavarro CountyNewton CountyNolan CountyNueces CountyOchiltree CountyOldham CountyOrange CountyPalo Pinto CountyPanola CountyParker CountyParmer CountyPecos CountyPolk CountyPotter CountyPresidio CountyRains CountyRandall CountyReagan CountyReal CountyRed River CountyReeves CountyRefugio CountyRoberts CountyRobertson CountyRockwall CountyRunnels CountyRusk CountySabine CountySan Augustine CountySan Jacinto CountySan Patricio CountySan Saba CountySchleicher CountyScurry CountyShackelford CountyShelby CountySherman CountySmith CountySomervell CountyStarr CountyStephens CountySterling CountyStonewall CountySutton CountySwisher CountyTarrant CountyTaylor CountyTerrell CountyTerry CountyThrockmorton CountyTitus CountyTom Green CountyTravis CountyTrinity CountyTyler CountyUpshur CountyUpton CountyUvalde CountyVal Verde CountyVan Zandt CountyVictoria CountyWalker CountyWaller CountyWard CountyWashington CountyWebb CountyWharton CountyWheeler CountyWichita CountyWilbarger CountyWillacy CountyWilliamson CountyWilson CountyWinkler CountyWise CountyWood CountyYoakum CountyYoung CountyZapata CountyZavala CountyRaeden Jacinto City data center · Proposed · 50 MW
Power50MW reported · stated
Site30acres

Who is behind it

ProjectRaeden Jacinto City data centerAlso: Houston Hyperscale (site marketing name)
Developer and teamRaeden
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. KPRC reported that Raeden is negotiating with the property owner, that city leaders unanimously oppose the plan, and that the project could require a special use permit. (KPRC Click2Houston, Sept. 11, 2026)

  2. At a town hall, residents largely opposed the plan. Raeden's president said the company aims to start construction in October and operate by March. The city manager said a special use permit with noise, emissions and bond requirements is planned. (ABC13 Houston (KTRK), Sept. 12, 2026)

  3. Jacinto City council approved Resolution 2026-10R opposing data centers in the city. (North Channel Star, July 10, 2026)

  4. Hoodline reported that a 30-acre heavy industrial lot at 4202 Fidelity St. was being marketed for data center use, with 40 MW deployable in 2026 and a path to 79 MW. (Hoodline, May 14, 2026)

Conflicts and open questions

  • Megawatt figures differ between Raeden (50 MW) and the site's sale materials (40-79 MW).
  • The street number, 30-acre size and marketing figures come from Hoodline's report on the Fidelity Street site; the Raeden reports (KPRC, ABC13) name only Fidelity Street, and KPRC says the owner chose Raeden over another company.
  • Hoodline gives the plant address as 4202 Fidelity St.; its report on the site being marketed does not name Raeden.

The full record

Status note
Raeden hopes to start redevelopment in Oct. 2026. City council passed a nonbinding resolution opposing data centers and plans a special use permit.
Power note
50 MW per Raeden. The site's sale brochure cited 40 MW deployable in 2026 and up to 79 MW within 24 months.
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.