Skybox Austin campus (Pflugerville)
A Skybox and Prologis data center campus in Pflugerville, with a 141,000-square-foot first building whose shell and fit-out work TDLR shows as finished and a second building registered. Also known as: Skybox Austin 1, Skybox Austin 2, Austin Data Center 1, LLC.
Who is behind it
Prologis
Austin Data Center 1, LLC (TDLR owner) (through Austin Data Center 1, LLC)
Austin Data Center 2, LLC (TDLR owner) (through Austin Data Center 2, LLC)
The record, newest first
TDLR lists a $28.5 million upfit of Building 1 with four data halls (registered Aug. 2022) as closed, with scheduled completion in Oct. 2024. (Texas Department of Licensing and Regulation, Aug. 19, 2022)
TDLR lists a $48 million fit-out of Austin 1 as complete and closed. (Texas Department of Licensing and Regulation, undated)
Skybox Austin 2, a $63 million, 148,500 sq ft shell building at 2515 S. Kenney Fort Blvd., Pflugerville, was registered with TDLR. (Texas Department of Licensing and Regulation, undated)
TDLR lists the Austin 1 shell building at 600 New Meister Lane as complete and the project closed. (Texas Department of Licensing and Regulation, undated)
Reports in June 2022 said Skybox and Prologis had broken ground on a 30 MW, 141,240 sq ft building in Pflugerville at Meister Lane and New Meister Lane, on a site master-planned for two such buildings. (DatacenterDynamics, undated; Baxtel, June 21, 2022)
Pflugerville City Council approved a PCDC grant agreement for a 141,000-square-foot Skybox data center, with up to $548 million in planned investment. (Pflugerville Community Development Corporation, March 9, 2022)
Conflicts and open questions
- Austin 2 is treated as the campus's second building based on DCD's two-building master plan and the shared Skybox ownership; TDLR gives it a separate Kenney Fort Boulevard address.
- TDLR event dates are the scheduled start/completion dates in the registration, not inspection dates.
- Separate from the Skybox PowerCampus Austin in Hutto (already tracked).
The full record
- Status note
- TDLR lists the Austin 1 shell and both fit-out projects as closed, the last scheduled to finish Oct. 2024; no operator announcement of service start was found, so operating status rests on these records. Austin 2 is registered with TDLR.
- Power note
- 30 MW reported for the first building.
- Evidence
- Primary public records
- Size class
- Under 50 MW (outside main scope; kept for completeness)