Data center campus · 2401 S. Dallas Ave., Lancaster, Dallas County, Texas

Skybox PowerCampus Dallas (Lancaster)

Under construction as of Jan. 20, 2026

Skybox is building a 300 MW, roughly 100-acre campus in Lancaster, with its first building being fitted out for a tenant. Also known as: LAN01.

Cite← Texas data centers
Anderson CountyAndrews CountyAngelina CountyAransas CountyArcher CountyArmstrong CountyAtascosa CountyAustin CountyBailey CountyBandera CountyBastrop CountyBaylor CountyBee CountyBell CountyBexar CountyBlanco CountyBorden CountyBosque CountyBowie CountyBrazoria CountyBrazos CountyBrewster CountyBriscoe CountyBrooks CountyBrown CountyBurleson CountyBurnet CountyCaldwell CountyCalhoun CountyCallahan CountyCameron CountyCamp CountyCarson CountyCass CountyCastro CountyChambers CountyCherokee CountyChildress CountyClay CountyCochran CountyCoke CountyColeman CountyCollin CountyCollingsworth CountyColorado CountyComal CountyComanche CountyConcho CountyCooke CountyCoryell CountyCottle CountyCrane CountyCrockett CountyCrosby CountyCulberson CountyDallam CountyDallas CountyDawson CountyDeaf Smith CountyDelta CountyDenton CountyDeWitt CountyDickens CountyDimmit CountyDonley CountyDuval CountyEastland CountyEctor CountyEdwards CountyEl Paso CountyEllis CountyErath CountyFalls CountyFannin CountyFayette CountyFisher CountyFloyd CountyFoard CountyFort Bend CountyFranklin CountyFreestone CountyFrio CountyGaines CountyGalveston CountyGarza CountyGillespie CountyGlasscock CountyGoliad CountyGonzales CountyGray CountyGrayson CountyGregg CountyGrimes CountyGuadalupe CountyHale CountyHall CountyHamilton CountyHansford CountyHardeman CountyHardin CountyHarris CountyHarrison CountyHartley CountyHaskell CountyHays CountyHemphill CountyHenderson CountyHidalgo CountyHill CountyHockley CountyHood CountyHopkins CountyHouston CountyHoward CountyHudspeth CountyHunt CountyHutchinson CountyIrion CountyJack CountyJackson CountyJasper CountyJeff Davis CountyJefferson CountyJim Hogg CountyJim Wells CountyJohnson CountyJones CountyKarnes CountyKaufman CountyKendall CountyKenedy CountyKent CountyKerr CountyKimble CountyKing CountyKinney CountyKleberg CountyKnox CountyLa Salle CountyLamar CountyLamb CountyLampasas CountyLavaca CountyLee CountyLeon CountyLiberty CountyLimestone CountyLipscomb CountyLive Oak CountyLlano CountyLoving CountyLubbock CountyLynn CountyMadison CountyMarion CountyMartin CountyMason CountyMatagorda CountyMaverick CountyMcCulloch CountyMcLennan CountyMcMullen CountyMedina CountyMenard CountyMidland CountyMilam CountyMills CountyMitchell CountyMontague CountyMontgomery CountyMoore CountyMorris CountyMotley CountyNacogdoches CountyNavarro CountyNewton CountyNolan CountyNueces CountyOchiltree CountyOldham CountyOrange CountyPalo Pinto CountyPanola CountyParker CountyParmer CountyPecos CountyPolk CountyPotter CountyPresidio CountyRains CountyRandall CountyReagan CountyReal CountyRed River CountyReeves CountyRefugio CountyRoberts CountyRobertson CountyRockwall CountyRunnels CountyRusk CountySabine CountySan Augustine CountySan Jacinto CountySan Patricio CountySan Saba CountySchleicher CountyScurry CountyShackelford CountyShelby CountySherman CountySmith CountySomervell CountyStarr CountyStephens CountySterling CountyStonewall CountySutton CountySwisher CountyTarrant CountyTaylor CountyTerrell CountyTerry CountyThrockmorton CountyTitus CountyTom Green CountyTravis CountyTrinity CountyTyler CountyUpshur CountyUpton CountyUvalde CountyVal Verde CountyVan Zandt CountyVictoria CountyWalker CountyWaller CountyWard CountyWashington CountyWebb CountyWharton CountyWheeler CountyWichita CountyWilbarger CountyWillacy CountyWilliamson CountyWilson CountyWinkler CountyWise CountyWood CountyYoakum CountyYoung CountyZapata CountyZavala CountySkybox PowerCampus Dallas (Lancaster) · Under construction · 300 MW
Power300MW reported · stated
Floor area1,000,000sq ft
Site100acres

Who is behind it

ProjectSkybox PowerCampus Dallas (Lancaster)Also: LAN01
Developer and teamSkybox Datacenters
Bandera Ventures
Principal Asset Management
Lancaster Data Center Campus, LP (TDLR owner)
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. A further $263 million fit-out of Building 1, scheduled through April 2027, is registered with TDLR. (Texas Department of Licensing and Regulation, Jan. 20, 2026)

  2. A $172 million tenant fit-out of Building 1 is registered with TDLR. (Texas Department of Licensing and Regulation, Feb. 25, 2025)

  3. A $214 million interior-improvements project for Building 1 is registered with TDLR. (Texas Department of Licensing and Regulation, Jan. 27, 2025)

  4. The 270,900 sq ft shell for Building 1 (LAN01) is registered with TDLR at an estimated $85 million. (Texas Department of Licensing and Regulation, June 7, 2024)

  5. Skybox, with Bandera Ventures and Principal Asset Management, starts work on a campus of up to 300 MW and 1 million sq ft near I-35E in Lancaster. (Dallas Innovates, Nov. 20, 2023)

Conflicts and open questions

  • Only Building 1 appears in the TDLR filings found; later buildings are not yet filed.

The full record

Status note
Skybox said work began in November 2023; TDLR filings for Building 1 fit-out run through April 2027.