Soluna Project Dorothy campus
A wind-powered compute campus near Silverton where Soluna runs nearly 100 MW of bitcoin hosting and mining and plans an adjacent AI/HPC data center (Dorothy 3). Also known as: Project Dorothy 1, Project Dorothy 2, Project Dorothy 3, Dorothy 1A, Dorothy 1B.
Who is behind it
Applied Digital (Dorothy 3 joint venture, pending)
The record, newest first
In an SEC 8-K, Soluna reported a definitive agreement with Applied Digital for a joint venture to build a 50 MW critical IT AI/HPC data center at Dorothy 3, with closing targeted by year-end 2026. (U.S. Securities and Exchange Commission (Soluna Holdings Form 8-K), Oct. 21, 2026; U.S. Securities and Exchange Commission (Soluna Holdings Exhibit 99.1), Oct. 21, 2026)
Soluna closed on 397 acres next to Dorothy 1 and 2 and the wind farm for Dorothy 3, which it describes as a campus of up to 300 MW. (Soluna Holdings, Aug. 24, 2026)
A Soluna investor presentation lists Dorothy 1A, 1B and 2 as operating and Dorothy 3 as an AI development site. It also describes buying the 150 MW Briscoe Wind Farm for $53 million. (Soluna Holdings, April 2, 2026)
Local reporting, as aggregated by Ground News, said Dorothy 2 was fully energized and the Silverton site now totals 98 MW. (Ground News (credits Caprock Courier), Nov. 20, 2025)
Business in Texas described Dorothy 2 in Briscoe County as doubling the earlier Dorothy 1 site and serving both bitcoin mining and AI. (Business in Texas (Office of the Governor), March 26, 2025)
Soluna said ERCOT had approved initial energization of the 48 MW Dorothy 2, to be commissioned in three phases through Q4 2025. (Soluna Holdings via Business Wire, March 25, 2025)
Conflicts and open questions
- Bitcoin facilities are included here because Soluna calls the site a data center campus and is developing an AI/HPC building on the same campus.
- The Caprock Courier, the original local source for the 98 MW figure, blocked fetching. The figure is cited through Ground News, which credits it.
- Coordinates are approximate, centered on Silverton.
The full record
- Status note
- Dorothy 1 and 2 are operating. Dorothy 3, a planned AI/HPC data center on adjacent land, is in development under a pending Soluna-Applied Digital joint venture.
- Power note
- Operating load per Soluna: Dorothy 1A 25 MW, 1B 25 MW, Dorothy 2 48 MW. Dorothy 3 is planned at 50 MW critical IT initially, with Soluna citing up to 300 MW long term.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)