Data center campus · Site not disclosed, Cameron County, Texas
Soluna Project Ellen
Proposed
as of Aug. 13, 2026
Soluna Holdings plans a wind-powered data center, first pitched for bitcoin hosting and AI work and now listed for AI, alongside a 145 MW wind farm in Cameron County.
Power145MW reported · stated
Who is behind it
ProjectSoluna Project Ellen
Developer and teamSoluna Holdings
End userNot found in the recordsNot yet named in any record or credited report we have found.
The record, newest first
Soluna's second-quarter 10-Q listed the project at 145 MW for AI use, with power purchase agreements being drafted. (Soluna Holdings (SEC EDGAR), Aug. 13, 2026)
Soluna's annual report placed Project Ellen in Cameron County at 100 MW, still in development. (Soluna Holdings (SEC EDGAR), March 30, 2026)
Soluna announced a power term sheet for a 100 MW data center to be built in two 50 MW phases next to a 145 MW wind farm in South Texas, aimed at bitcoin hosting and AI or HPC work. (Business Wire (Soluna Holdings release), April 17, 2025)
Conflicts and open questions
- Wind farm owner is unnamed in Soluna's filings and releases.
- Soluna also lists a separate Project Hedy in Cameron County; that one is not part of this record.
- The project was originally framed for bitcoin hosting as well as AI; the Q2 2026 10-Q lists AI only.
The full record
- Status note
- Soluna lists the project as in development with a signed power term sheet; its Q2 2026 10-Q says power purchase agreements are being drafted.
- Power note
- Soluna's Q2 2026 10-Q lists 145 MW, matching the 145 MW wind farm; its April 2025 announcement and FY2025 10-K gave 100 MW in two 50 MW phases.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)