Data center campus · Site not disclosed, Childress County, Texas
Soluna Project Fei
Proposed
as of Aug. 13, 2026
Soluna Holdings is developing a data center paired with a 240 MW solar farm in Childress County, once listed for bitcoin hosting or AI and now listed for AI.
Power240MW reported · stated
Who is behind it
ProjectSoluna Project Fei
Developer and teamSoluna Holdings
End userNot found in the recordsNot yet named in any record or credited report we have found.
The record, newest first
Soluna's second-quarter 10-Q listed Project Fei at 240 MW for AI use, with power purchase agreements being drafted. (Soluna Holdings (SEC EDGAR), Aug. 13, 2026)
Soluna's annual report placed Project Fei in Childress County at 100 MW, in development for bitcoin hosting or AI and HPC. (Soluna Holdings (SEC EDGAR), March 30, 2026)
Soluna announced Project Fei, a 100 MW data center to sit beside a 240 MW solar farm in northern Texas, developed with an unnamed energy infrastructure investor. (Business Wire (Soluna Holdings release), Aug. 26, 2025)
Conflicts and open questions
- Unrelated to IREN's Childress campus or the TDLR-listed Project Hyper in Childress already tracked.
The full record
- Status note
- Soluna says land acquisition, power contract talks and ERCOT interconnection planning are under way; power purchase agreements were being drafted as of the Q2 2026 10-Q.
- Power note
- Q2 2026 10-Q lists 240 MW, matching the 240 MW solar farm; the August 2025 announcement and FY2025 10-K gave 100 MW.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)