Soluna plans a data center beside a wind farm in Cameron County, first pitched for bitcoin mining and AI and now listed in its filings as an AI project.
Power198MW reported · record
Who is behind it
ProjectSoluna Project Hedy
Developer and teamSoluna Holdings
End userNot found in the recordsNot yet named in any record or credited report we have found.
The record, newest first
Soluna's quarterly filing listed Hedy at 198 MW, co-located with a 198 MW wind farm, still in development. (Soluna Holdings, Inc. (SEC Form 10-Q), Aug. 13, 2026)
Soluna announced Project Hedy, a 120 MW data center to sit next to a 200 MW wind farm owned by an unnamed multinational partner in Cameron County. (Soluna Holdings (Business Wire), April 8, 2025; Soluna Holdings, Inc. (SEC Form 8-K exhibit 99.1), April 8, 2025)
Conflicts and open questions
- Earlier plans covered bitcoin hosting as well as AI; the latest filing lists AI as the intended use.
The full record
- Status note
- Development stage; power term sheet signed and power purchase agreements under negotiation.
- Power note
- Announced at 120 MW in two 60 MW phases (April 2025); the Q2 2026 10-Q lists 198 MW for AI.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)