Data center campus · Northeast Rio Grande Valley; site not disclosed, Willacy County, Texas

Soluna Project Kati campus

Operating as of Feb. 2026

Soluna's wind-powered campus in Willacy County opened its first phase as a bitcoin mining data center in February 2026, and the company plans a second, AI and HPC phase on the same site with Metrobloks. Also known as: Kati 1, Kati 2.

Cite← Texas data centers
Anderson CountyAndrews CountyAngelina CountyAransas CountyArcher CountyArmstrong CountyAtascosa CountyAustin CountyBailey CountyBandera CountyBastrop CountyBaylor CountyBee CountyBell CountyBexar CountyBlanco CountyBorden CountyBosque CountyBowie CountyBrazoria CountyBrazos CountyBrewster CountyBriscoe CountyBrooks CountyBrown CountyBurleson CountyBurnet CountyCaldwell CountyCalhoun CountyCallahan CountyCameron CountyCamp CountyCarson CountyCass CountyCastro CountyChambers CountyCherokee CountyChildress CountyClay CountyCochran CountyCoke CountyColeman CountyCollin CountyCollingsworth CountyColorado CountyComal CountyComanche CountyConcho CountyCooke CountyCoryell CountyCottle CountyCrane CountyCrockett CountyCrosby CountyCulberson CountyDallam CountyDallas CountyDawson CountyDeaf Smith CountyDelta CountyDenton CountyDeWitt CountyDickens CountyDimmit CountyDonley CountyDuval CountyEastland CountyEctor CountyEdwards CountyEl Paso CountyEllis CountyErath CountyFalls CountyFannin CountyFayette CountyFisher CountyFloyd CountyFoard CountyFort Bend CountyFranklin CountyFreestone CountyFrio CountyGaines CountyGalveston CountyGarza CountyGillespie CountyGlasscock CountyGoliad CountyGonzales CountyGray CountyGrayson CountyGregg CountyGrimes CountyGuadalupe CountyHale CountyHall CountyHamilton CountyHansford CountyHardeman CountyHardin CountyHarris CountyHarrison CountyHartley CountyHaskell CountyHays CountyHemphill CountyHenderson CountyHidalgo CountyHill CountyHockley CountyHood CountyHopkins CountyHouston CountyHoward CountyHudspeth CountyHunt CountyHutchinson CountyIrion CountyJack CountyJackson CountyJasper CountyJeff Davis CountyJefferson CountyJim Hogg CountyJim Wells CountyJohnson CountyJones CountyKarnes CountyKaufman CountyKendall CountyKenedy CountyKent CountyKerr CountyKimble CountyKing CountyKinney CountyKleberg CountyKnox CountyLa Salle CountyLamar CountyLamb CountyLampasas CountyLavaca CountyLee CountyLeon CountyLiberty CountyLimestone CountyLipscomb CountyLive Oak CountyLlano CountyLoving CountyLubbock CountyLynn CountyMadison CountyMarion CountyMartin CountyMason CountyMatagorda CountyMaverick CountyMcCulloch CountyMcLennan CountyMcMullen CountyMedina CountyMenard CountyMidland CountyMilam CountyMills CountyMitchell CountyMontague CountyMontgomery CountyMoore CountyMorris CountyMotley CountyNacogdoches CountyNavarro CountyNewton CountyNolan CountyNueces CountyOchiltree CountyOldham CountyOrange CountyPalo Pinto CountyPanola CountyParker CountyParmer CountyPecos CountyPolk CountyPotter CountyPresidio CountyRains CountyRandall CountyReagan CountyReal CountyRed River CountyReeves CountyRefugio CountyRoberts CountyRobertson CountyRockwall CountyRunnels CountyRusk CountySabine CountySan Augustine CountySan Jacinto CountySan Patricio CountySan Saba CountySchleicher CountyScurry CountyShackelford CountyShelby CountySherman CountySmith CountySomervell CountyStarr CountyStephens CountySterling CountyStonewall CountySutton CountySwisher CountyTarrant CountyTaylor CountyTerrell CountyTerry CountyThrockmorton CountyTitus CountyTom Green CountyTravis CountyTrinity CountyTyler CountyUpshur CountyUpton CountyUvalde CountyVal Verde CountyVan Zandt CountyVictoria CountyWalker CountyWaller CountyWard CountyWashington CountyWebb CountyWharton CountyWheeler CountyWichita CountyWilbarger CountyWillacy CountyWilliamson CountyWilson CountyWinkler CountyWise CountyWood CountyYoakum CountyYoung CountyZapata CountyZavala CountySoluna Project Kati campus · Operating · 433 MW
Power433MW reported · record

Who is behind it

ProjectSoluna Project Kati campusAlso: Kati 1, Kati 2
Developer and teamSoluna Holdings (through Soluna Digital, Inc.; Soluna KKSL JVCo LLC)
Metrobloks (Kati 2 joint venture) (through Soluna MB KK II JVCo, LLC)
End userGalaxy Digital (initial Kati 1 hosting customer)

The record, newest first

  1. Soluna reported 69 MW of Kati 1 built, with the remaining 14 MW expected in August 2026. (Soluna Holdings, Inc. (SEC Form 10-Q), Aug. 13, 2026)

  2. Soluna and a Metrobloks affiliate signed the joint venture agreement for Kati 2, an AI and HPC campus planned at about 100 MW of IT load in phase I and about 250 MW in phase II. (Soluna Holdings, Inc. (SEC Form 10-Q), Aug. 13, 2026)

  3. Soluna began energizing Kati 1, an 83 MW bitcoin hosting phase powered by the adjacent wind farm. (Soluna Holdings (Business Wire), Feb. 10, 2026)

  4. Construction started on the campus, which sits next to the Las Majadas wind project. (Soluna Computing, Nov. 17, 2025; The Texas Tribune (via KSAT), Oct. 21, 2025)

  5. Soluna closed financing with Spring Lane Capital for the first 35 MW of Kati 1. (Soluna Holdings, Inc. (SEC Form 10-K), March 30, 2026)

Conflicts and open questions

  • Bitcoin mining data center (Kati 1); Kati 2 is planned for AI/HPC per Soluna's SEC filings.
  • Texas Tribune reported the county judge cited taxable value as the main local benefit; no abatement was mentioned.

The full record

Status note
Kati 1 (83 MW, bitcoin hosting) began operating in February 2026, with 69 MW built by June 30, 2026 and the last 14 MW expected in August 2026; Kati 2 (AI/HPC) is in development.
Power note
83 MW for Kati 1, plus Kati 2 planned at about 100 MW of critical IT load in phase I and about 250 MW in phase II under the Metrobloks joint venture (Q2 2026 10-Q). Earlier company materials described a 166 MW campus in two 83 MW phases.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.