STACK DFW01 Plano campus
A 45-acre STACK Infrastructure campus in west Plano with two operating buildings (32 MW) and a planned 48 MW third building, for 80 MW of critical capacity in all. Also known as: DFW01A, DFW01B, DFW01C.
Who is behind it
The record, newest first
STACK's DFW01 page lists 80 MW of critical capacity on 45 acres across DFW01A (21 MW, 318,000 sq ft), DFW01B (11 MW, 156,000 sq ft) and the DFW01C expansion (48 MW, 332,000 sq ft); its brochure gives DFW01C 16 acres. (STACK Infrastructure, Oct. 2, 2026; STACK Infrastructure, undated)
Plano's Planning and Zoning Commission approved a preliminary site plan and a 20% parking reduction for a third STACK data center at 5601 W. Spring Creek Parkway, reported at 363,000 square feet and 48 MW. (Community Impact, July 24, 2025)
STACK said its two Plano data centers then totaled 32 MW and almost 400,000 square feet, with room for another 50 MW on 16 adjacent acres. (STACK Infrastructure (Business Wire), Sept. 8, 2020)
Conflicts and open questions
- Square footage for DFW01C is 332,000 on STACK's page and brochure and 363,000 in reporting on city documents.
- STACK states 80 MW as critical capacity, so mw and it_mw are the same figure.
- The 2020 release dates are taken from the Business Wire URL; the page shows no dateline.
The full record
- Status note
- Two buildings (32 MW) are in service; a third, DFW01C (48 MW), received preliminary site plan approval from Plano's Planning and Zoning Commission in July 2025.
- Power note
- 80 MW includes the planned 48 MW DFW01C; about 32 MW is in operation.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)