STACK DFW02 Lancaster campus
A six-building, 220 MW STACK campus on more than 100 acres in Lancaster, south of Dallas. Also known as: DFW02, South Dallas campus.
Who is behind it
The record, newest first
Scheduled start for a second building, DFW02A-P2, at 1100 E. Belt Line Road, about 360,000 square feet and $202 million, with completion set for March 2028. (Texas Department of Licensing and Regulation (TABS), Oct. 29, 2026)
Scheduled construction start for the first building, DFW02A, a two-story, roughly 360,000-square-foot data center at 1000 E. Belt Line Road, per its state registration. (Texas Department of Licensing and Regulation (TABS), Oct. 29, 2026)
STACK announced a 220 MW, six-building campus of about 1.5 million square feet on more than 100 acres in Lancaster, with Oncor power through its own substation and first delivery targeted for mid-2026. (STACK Infrastructure, April 29, 2024; DatacenterDynamics, April 30, 2024)
Conflicts and open questions
- Status relies on TDLR scheduled start dates; no independent confirmation of construction was found.
- The lead's six building names (DFW02A-F) match the six buildings STACK announced, but only two TDLR registrations were found.
The full record
- Status note
- State building registrations put the first building under way from May 2025 and a second from January 2026; no groundbreaking report was found.
- Power note
- Developer figure for six 36 MW buildings; STACK's brochure is reported to cite up to 300 MW.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)