Data center campus · Colchester Industrial Park, near Dumfries and Minnieville roads, Prince William, Virginia

Amazon-linked data center site, Colchester Industrial Park

Approved as of June 2024

Supervisors rezoned a 64-acre industrial park in mid-county Prince William for three data centers up to 95 feet tall and a substation, and an Amazon-linked company bought most of it for about $53.5 million. Also known as: Mid-County Industrial Park.

Cite← Virginia data centers
AccomackAlbemarleAlexandriaAlleghanyAmeliaAmherstAppomattoxArlingtonAugustaBathBedfordBlandBotetourtBristolBrunswickBuchananBuckinghamBuena VistaCampbellCarolineCarrollCharles CityCharlotteCharlottesvilleChesapeakeChesterfieldClarkeColonial HeightsCovingtonCraigCulpeperCumberlandDanvilleDickensonDinwiddieEmporiaEssexFairfaxFairfax (city)Falls ChurchFauquierFloydFluvannaFranklinFranklin (city)FrederickFredericksburgGalaxGilesGloucesterGoochlandGraysonGreeneGreensvilleHalifaxHamptonHanoverHarrisonburgHenricoHenryHighlandHopewellIsle of WightJames CityKing and QueenKing GeorgeKing WilliamLancasterLeeLexingtonLoudounLouisaLunenburgLynchburgMadisonManassasManassas ParkMartinsvilleMathewsMecklenburgMiddlesexMontgomeryNelsonNew KentNewport NewsNorfolkNorthamptonNorthumberlandNortonNottowayOrangePagePatrickPetersburgPittsylvaniaPoquosonPortsmouthPowhatanPrince EdwardPrince GeorgePrince WilliamPulaskiRadfordRappahannockRichmondRichmond (city)RoanokeRoanoke (city)RockbridgeRockinghamRussellSalemScottShenandoahSmythSouthamptonSpotsylvaniaStaffordStauntonSuffolkSurrySussexTazewellVirginia BeachWarrenWashingtonWaynesboroWestmorelandWilliamsburgWinchesterWiseWytheYorkAmazon-linked data center site, Colchester Industrial Park · Approved
PowerNot statedNot reported in the records found
Site64acres

Who is behind it

ProjectAmazon-linked data center site, Colchester Industrial ParkAlso: Mid-County Industrial Park
Developer and teamMinnieville Capital Acquisitions LLC (reported as Amazon-affiliated)
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. Property records showed that a company sharing a Seattle post office box with Amazon Data Services had bought 16 of the park's 21 parcels for about $53.5 million; Amazon did not confirm the purchase. (Prince William Times, Sept. 24, 2024)

  2. Supervisors rezoned the parcels for three data center buildings up to 95 feet tall and a substation. (Prince William Times, Sept. 24, 2024)

Conflicts and open questions

  • The site is under 100 acres and no power figure was reported, so it is below the tracker's size thresholds.
  • The buyer's link to Amazon rests on a shared mailing address on tax records; Amazon did not confirm the purchase, so entity is left null.
  • About 2 miles south of the former Parsons site (aws-parsons-independent-hill); the two were rezoned separately and are kept as separate projects.

The full record

Status note
Rezoned in June 2024 for three data centers and a substation; no construction record was found.
Power note
No power figure was published.
Evidence
News reports; primary records not yet obtained
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.