Data center campus · 13860 and 13876 Redskin Drive, Herndon (Floris area, east of Route 28), Fairfax, Virginia

Renaissance Technology Park (Amazon IAD-500/501)

Under construction as of Dec. 16, 2025

A roughly 60-acre former warehouse park near Dulles Airport that Starwood is converting into four data center buildings leased to Amazon. Also known as: IAD-500, IAD-501.

Cite← Virginia data centers
AccomackAlbemarleAlexandriaAlleghanyAmeliaAmherstAppomattoxArlingtonAugustaBathBedfordBlandBotetourtBristolBrunswickBuchananBuckinghamBuena VistaCampbellCarolineCarrollCharles CityCharlotteCharlottesvilleChesapeakeChesterfieldClarkeColonial HeightsCovingtonCraigCulpeperCumberlandDanvilleDickensonDinwiddieEmporiaEssexFairfaxFairfax (city)Falls ChurchFauquierFloydFluvannaFranklinFranklin (city)FrederickFredericksburgGalaxGilesGloucesterGoochlandGraysonGreeneGreensvilleHalifaxHamptonHanoverHarrisonburgHenricoHenryHighlandHopewellIsle of WightJames CityKing and QueenKing GeorgeKing WilliamLancasterLeeLexingtonLoudounLouisaLunenburgLynchburgMadisonManassasManassas ParkMartinsvilleMathewsMecklenburgMiddlesexMontgomeryNelsonNew KentNewport NewsNorfolkNorthamptonNorthumberlandNortonNottowayOrangePagePatrickPetersburgPittsylvaniaPoquosonPortsmouthPowhatanPrince EdwardPrince GeorgePrince WilliamPulaskiRadfordRappahannockRichmondRichmond (city)RoanokeRoanoke (city)RockbridgeRockinghamRussellSalemScottShenandoahSmythSouthamptonSpotsylvaniaStaffordStauntonSuffolkSurrySussexTazewellVirginia BeachWarrenWashingtonWaynesboroWestmorelandWilliamsburgWinchesterWiseWytheYorkRenaissance Technology Park (Amazon IAD-500/501) · Under construction
PowerNot statedNot reported in the records found
Floor area2,100,000sq ft
Site60acres

Who is behind it

ProjectRenaissance Technology Park (Amazon IAD-500/501)Also: IAD-500, IAD-501
Developer and teamStarwood Capital Group (affiliate)
End userAmazon Web Services

The record, newest first

  1. A county planner's letter, posted Dec. 15, found the former church parcel suitable for a data center; Starwood's consultant had filed a DEQ air permit application in November, and the plan calls for buildings of 60 MW and 32 MW on Towerview Road. (FFXnow, Dec. 16, 2025)

  2. County staff approved a site plan for two buildings on the former church parcel inside the park. (FFXnow, Dec. 16, 2025)

  3. Virginia DEQ issued Amazon Data Services a permit for 74 generator sets at the IAD-500 and IAD-501 campus (registration 74300). (Virginia Department of Environmental Quality, March 12, 2025)

  4. Reporting, first by the Washington Business Journal, identified Amazon as the operator; Amazon Data Services had sought DEQ air permits and county building permits. (FFXnow, Sept. 27, 2024)

  5. A site plan was filed for the first phase: a three-story data center, a 6-acre substation and support buildings. (FFXnow, Sept. 27, 2024)

  6. A Starwood affiliate bought the adjoining former Word of Grace Christian Church property, which includes former NFL practice fields, for $25 million (its size is reported as about 8 or about 30 acres). (FFXnow, Dec. 16, 2025; Commercial Observer, Dec. 3, 2025)

  7. Fairfax supervisors approved a special exception for Starwood's plan to replace the park's warehouses with four data center buildings totaling 2.1 million sq ft. (FFXnow, Sept. 27, 2024)

Conflicts and open questions

  • The former church parcel (13832 Redskin Drive; buildings at 2850 and 2860 Towerview Road) is treated as an expansion of this campus because it is surrounded by the park and has the same owner; whether Amazon will use those buildings was unclear in December 2025 reporting.
  • Acreage of the original park is reported as nearly 60 acres; the church parcel is reported as about 8 acres (Commercial Observer) or about 30 acres (FFXnow).
  • Fairfax County adopted new data center zoning rules on Sept. 10, 2024, after this project's 2022 approval.

The full record

Status note
FFXnow reported in December 2025 that the park was already being redeveloped with data centers for Amazon.
Power note
No campus-wide power figure is published. FFXnow reported that the adjoining former church parcel Starwood is adding has two planned buildings of 60 MW and 32 MW.
Evidence
Primary public records
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.