Approved · Google's largest planned Chesterfield site, about 850 acres in Moseley, is to hold four data center buildings, with the first expected to open in 2029. Also known as: Project Skye, Skyward Holdings.

← Virginia data centers
Accomack CountyAlbemarle CountyAlexandria CountyAlleghany CountyAmelia CountyAmherst CountyAppomattox CountyArlington CountyAugusta CountyBath CountyBedford CountyBland CountyBotetourt CountyBristol CountyBrunswick CountyBuchanan CountyBuckingham CountyBuena Vista CountyCampbell CountyCaroline CountyCarroll CountyCharles City CountyCharlotte CountyCharlottesville CountyChesapeake CountyChesterfield CountyClarke CountyColonial Heights CountyCovington CountyCraig CountyCulpeper CountyCumberland CountyDanville CountyDickenson CountyDinwiddie CountyEmporia CountyEssex CountyFairfax CountyFairfax (city) CountyFalls Church CountyFauquier CountyFloyd CountyFluvanna CountyFranklin CountyFranklin (city) CountyFrederick CountyFredericksburg CountyGalax CountyGiles CountyGloucester CountyGoochland CountyGrayson CountyGreene CountyGreensville CountyHalifax CountyHampton CountyHanover CountyHarrisonburg CountyHenrico CountyHenry CountyHighland CountyHopewell CountyIsle of Wight CountyJames City CountyKing and Queen CountyKing George CountyKing William CountyLancaster CountyLee CountyLexington CountyLoudoun CountyLouisa CountyLunenburg CountyLynchburg CountyMadison CountyManassas CountyManassas Park CountyMartinsville CountyMathews CountyMecklenburg CountyMiddlesex CountyMontgomery CountyNelson CountyNew Kent CountyNewport News CountyNorfolk CountyNorthampton CountyNorthumberland CountyNorton CountyNottoway CountyOrange CountyPage CountyPatrick CountyPetersburg CountyPittsylvania CountyPoquoson CountyPortsmouth CountyPowhatan CountyPrince Edward CountyPrince George CountyPrince William CountyPulaski CountyRadford CountyRappahannock CountyRichmond CountyRichmond (city) CountyRoanoke CountyRoanoke (city) CountyRockbridge CountyRockingham CountyRussell CountySalem CountyScott CountyShenandoah CountySmyth CountySouthampton CountySpotsylvania CountyStafford CountyStaunton CountySuffolk CountySurry CountySussex CountyTazewell CountyVirginia Beach CountyWarren CountyWashington CountyWaynesboro CountyWestmoreland CountyWilliamsburg CountyWinchester CountyWise CountyWythe CountyYork CountyGoogle Chesterfield campus (Project Skye) · Approved
Status
Approved · as of June 2025
Location
4201 Moseley Road, Moseley, near Magnolia Green · Chesterfield
Status note
Zoning and a tax agreement were approved in the first half of 2025; construction of the first building is expected to start in 2027.
Power
Not reported
Google has not disclosed megawatt capacity.
Land
850 acres
Developer and team
Google (through Skyward Holdings LLC)
End user
Google
Utility
Dominion Energy
Incentives
An equipment tax rate freeze at 24 cents per $100 for 10 years, with two 10-year extensions, approved by supervisors in June 2025.
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.

Updates, newest first

  1. Aug. 26, 2026 County officials said the first building should start construction in 2027 and open in 2029. (Richmond BizSense, Aug. 27, 2026)
  2. Aug. 27, 2025 Google disclosed that it controls Skyward Holdings and said it had no immediate plans to build there. (Richmond BizSense, Aug. 28, 2025)
  3. June 2025 Supervisors approved a tax-incentive agreement for the then code-named project; its tie to Google was not public. (Richmond BizSense, Aug. 28, 2025)