Data center campus · Off Mills Drive along Cosner Drive, Cosner's Corner area, Spotsylvania, Virginia

PowerHouse 95 campus

Under construction as of July 2024

A 145-acre PowerHouse data center campus at Cosner's Corner announced at up to 800 MW, which broke ground in 2024.

Cite← Virginia data centers
AccomackAlbemarleAlexandriaAlleghanyAmeliaAmherstAppomattoxArlingtonAugustaBathBedfordBlandBotetourtBristolBrunswickBuchananBuckinghamBuena VistaCampbellCarolineCarrollCharles CityCharlotteCharlottesvilleChesapeakeChesterfieldClarkeColonial HeightsCovingtonCraigCulpeperCumberlandDanvilleDickensonDinwiddieEmporiaEssexFairfaxFairfax (city)Falls ChurchFauquierFloydFluvannaFranklinFranklin (city)FrederickFredericksburgGalaxGilesGloucesterGoochlandGraysonGreeneGreensvilleHalifaxHamptonHanoverHarrisonburgHenricoHenryHighlandHopewellIsle of WightJames CityKing and QueenKing GeorgeKing WilliamLancasterLeeLexingtonLoudounLouisaLunenburgLynchburgMadisonManassasManassas ParkMartinsvilleMathewsMecklenburgMiddlesexMontgomeryNelsonNew KentNewport NewsNorfolkNorthamptonNorthumberlandNortonNottowayOrangePagePatrickPetersburgPittsylvaniaPoquosonPortsmouthPowhatanPrince EdwardPrince GeorgePrince WilliamPulaskiRadfordRappahannockRichmondRichmond (city)RoanokeRoanoke (city)RockbridgeRockinghamRussellSalemScottShenandoahSmythSouthamptonSpotsylvaniaStaffordStauntonSuffolkSurrySussexTazewellVirginia BeachWarrenWashingtonWaynesboroWestmorelandWilliamsburgWinchesterWiseWytheYorkPowerHouse 95 campus · Under construction · 800 MW
Power800MW reported · stated
Floor area3,500,000sq ft
Site145acres

Who is behind it

ProjectPowerHouse 95 campus
Developer and teamPowerHouse Data Centers (American Real Estate Partners)
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. PowerHouse broke ground on the campus. (DatacenterDynamics, undated; DatacenterDynamics, undated)

  2. PowerHouse said it had closed on 145 acres along the I-95 corridor for a campus of up to eight buildings and 3.5 million sq ft, with the first 150 MW substation expected by October 2025. (PowerHouse Data Centers (PR Newswire), Jan. 23, 2024)

Conflicts and open questions

  • DCD (undated copy) reported a later Army Corps (Norfolk District) filing for a three-building second phase with about 2.3 acres of wetland impact; date it before adding as an event.
  • No county zoning record was opened; whether the site was by-right is not stated.
  • Up to 3.5 million sq ft in eight buildings at announcement; a later filing described up to seven buildings and 1.75 million sq ft.

The full record

Status note
Ground was broken in mid-2024; a second phase was filed with the Army Corps later.
Power note
The developer announced up to 800 MW over three substations, with a first 150 MW phase due by October 2025; a later DCD report gave up to 300 MW, possibly 900 MW eventually. Figures conflict.
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.