Data center campus · 7980 and 7990 Quantum Drive, Tysons (Vienna), Fairfax, Virginia

Serverfarm Vienna Cloud campus, Tysons

Proposed as of May 4, 2026

Serverfarm proposes to replace two 1970s office buildings and a parking garage on Quantum Drive in Tysons with two data center buildings totaling about 316,000 sq ft. Also known as: Vienna Cloud.

Cite← Virginia data centers
AccomackAlbemarleAlexandriaAlleghanyAmeliaAmherstAppomattoxArlingtonAugustaBathBedfordBlandBotetourtBristolBrunswickBuchananBuckinghamBuena VistaCampbellCarolineCarrollCharles CityCharlotteCharlottesvilleChesapeakeChesterfieldClarkeColonial HeightsCovingtonCraigCulpeperCumberlandDanvilleDickensonDinwiddieEmporiaEssexFairfaxFairfax (city)Falls ChurchFauquierFloydFluvannaFranklinFranklin (city)FrederickFredericksburgGalaxGilesGloucesterGoochlandGraysonGreeneGreensvilleHalifaxHamptonHanoverHarrisonburgHenricoHenryHighlandHopewellIsle of WightJames CityKing and QueenKing GeorgeKing WilliamLancasterLeeLexingtonLoudounLouisaLunenburgLynchburgMadisonManassasManassas ParkMartinsvilleMathewsMecklenburgMiddlesexMontgomeryNelsonNew KentNewport NewsNorfolkNorthamptonNorthumberlandNortonNottowayOrangePagePatrickPetersburgPittsylvaniaPoquosonPortsmouthPowhatanPrince EdwardPrince GeorgePrince WilliamPulaskiRadfordRappahannockRichmondRichmond (city)RoanokeRoanoke (city)RockbridgeRockinghamRussellSalemScottShenandoahSmythSouthamptonSpotsylvaniaStaffordStauntonSuffolkSurrySussexTazewellVirginia BeachWarrenWashingtonWaynesboroWestmorelandWilliamsburgWinchesterWiseWytheYorkServerfarm Vienna Cloud campus, Tysons · Proposed
PowerNot statedNot reported in the records found
Floor area316,228sq ft
Site14.4acres

Who is behind it

ProjectServerfarm Vienna Cloud campus, TysonsAlso: Vienna Cloud
Developer and teamServerfarm (applicant SF DC1 LLC)
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. Planning Commission public hearing scheduled. (Patch (McLean), May 11, 2026)

  2. Fairfax County accepted SF DC1 LLC's proffered condition amendment and special exception application, which seeks a smaller Metro buffer, a higher floor area ratio, setbacks below the current requirement and less tree canopy. (Patch (McLean), May 11, 2026)

  3. Serverfarm bought the Quantum Drive properties from Legacy Investing and Element Critical. (DatacenterDynamics, Feb. 2026)

Conflicts and open questions

  • power is not reported and the site is 14.4 acres, under the 100-acre floor used when power is unknown.
  • The site is about 0.9 miles from the Tysons Corner Metro entrance, inside the county's 1-mile buffer, which the applicant asks to reduce.
  • An existing data center at 7790 Quantum Drive in the same complex is described by DCD as Equinix DC7; whether Serverfarm operates any existing data center here was not confirmed.

The full record

Status note
Fairfax County accepted the application on May 4, 2026; a Planning Commission hearing was set for Nov. 18, 2026.
Power note
No power figure has been reported for the proposal.
Evidence
News reports; primary records not yet obtained
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.