Data center campus · 19509 Belmont Ridge Road, Ashburn (west of Belmont Ridge Road, south of Route 7), Loudoun, Virginia

Vantage Data Centers Ashburn III (VA3) campus

Proposed as of Oct. 2026

Vantage's third Ashburn campus, planned on 134 acres at 19509 Belmont Ridge Road for seven multi-story buildings and 288 MW of IT load fed by two Dominion substations. Also known as: VA3.

Cite← Virginia data centers
AccomackAlbemarleAlexandriaAlleghanyAmeliaAmherstAppomattoxArlingtonAugustaBathBedfordBlandBotetourtBristolBrunswickBuchananBuckinghamBuena VistaCampbellCarolineCarrollCharles CityCharlotteCharlottesvilleChesapeakeChesterfieldClarkeColonial HeightsCovingtonCraigCulpeperCumberlandDanvilleDickensonDinwiddieEmporiaEssexFairfaxFairfax (city)Falls ChurchFauquierFloydFluvannaFranklinFranklin (city)FrederickFredericksburgGalaxGilesGloucesterGoochlandGraysonGreeneGreensvilleHalifaxHamptonHanoverHarrisonburgHenricoHenryHighlandHopewellIsle of WightJames CityKing and QueenKing GeorgeKing WilliamLancasterLeeLexingtonLoudounLouisaLunenburgLynchburgMadisonManassasManassas ParkMartinsvilleMathewsMecklenburgMiddlesexMontgomeryNelsonNew KentNewport NewsNorfolkNorthamptonNorthumberlandNortonNottowayOrangePagePatrickPetersburgPittsylvaniaPoquosonPortsmouthPowhatanPrince EdwardPrince GeorgePrince WilliamPulaskiRadfordRappahannockRichmondRichmond (city)RoanokeRoanoke (city)RockbridgeRockinghamRussellSalemScottShenandoahSmythSouthamptonSpotsylvaniaStaffordStauntonSuffolkSurrySussexTazewellVirginia BeachWarrenWashingtonWaynesboroWestmorelandWilliamsburgWinchesterWiseWytheYorkVantage Data Centers Ashburn III (VA3) campus · Proposed · 288 MW
Power288MW reported · stated
Floor area2,300,000sq ft
Site134acres
IT load288MW

Who is behind it

ProjectVantage Data Centers Ashburn III (VA3) campusAlso: VA3
Developer and teamVantage Data Centers
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. Vantage's campus page (last updated June 2025) lists VA3 at 19509 Belmont Ridge Road with 288 MW of critical IT capacity, about 2.3 million sq ft in seven buildings and two dedicated Dominion substations, described as coming soon. (Vantage Data Centers, June 4, 2025)

  2. Commercial Property Executive reported that VA3 would add seven multi-story buildings and 288 MW, that Vantage bought the 134-acre site in 2022 for $180 million, and, citing DCD, that it had applied to develop the site. (Commercial Property Executive, April 24, 2024)

Conflicts and open questions

  • Square footage varies: Vantage's page gives about 2.3 million and also 'more than 2 million'; the Commercial Property Executive article gives 2.3 million in one place and 2.8 million in another.
  • The point is placed from the company address and is approximate.

The full record

Status note
Vantage describes the campus as coming soon; no opened record shows construction or completion.
Power note
Company figure: critical IT capacity at full build-out.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.