Data center campus · 1 Quarry Road, Brisbane (site in unincorporated San Mateo County; about 104 acres proposed for annexation to the city), San Mateo County, California

Guadalupe Quarry data center (now Quarry Innovation Center)

Withdrawn as of Aug. 6, 2026

A 180,000-square-foot data center proposed for the Guadalupe Quarry in 2025 was dropped; the site's plan is now light fabrication and advanced manufacturing. Also known as: Guadalupe Quarry Redevelopment Project, Quarry Innovation Center.

Cite← California data centers
Alameda CountyAlpine CountyAmador CountyButte CountyCalaveras CountyColusa CountyContra Costa CountyDel Norte CountyEl Dorado CountyFresno CountyGlenn CountyHumboldt CountyImperial CountyInyo CountyKern CountyKings CountyLake CountyLassen CountyLos Angeles CountyMadera CountyMarin CountyMariposa CountyMendocino CountyMerced CountyModoc CountyMono CountyMonterey CountyNapa CountyNevada CountyOrange CountyPlacer CountyPlumas CountyRiverside CountySacramento CountySan Benito CountySan Bernardino CountySan Diego CountySan Francisco CountySan Joaquin CountySan Luis Obispo CountySan Mateo CountySanta Barbara CountySanta Clara CountySanta Cruz CountyShasta CountySierra CountySiskiyou CountySolano CountySonoma CountyStanislaus CountySutter CountyTehama CountyTrinity CountyTulare CountyTuolumne CountyVentura CountyYolo CountyYuba CountyGuadalupe Quarry data center (now Quarry Innovation Center) · Withdrawn
PowerNot statedNot reported in the records found
Floor area180,000sq ft
Site153acres

Who is behind it

ProjectGuadalupe Quarry data center (now Quarry Innovation Center)Also: Guadalupe Quarry Redevelopment Project, Quarry Innovation Center
Developer and teamOrchard Partners, LLC
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. Brisbane's corrected notice for the revised project says the plan contains no data center and describes a building of about 895,000 sq ft. Comments ran to Sept. 8; the city's page, in an earlier update, anticipated a Draft EIR in fall 2026. (City of Brisbane (posted by Orchard Partners), Aug. 6, 2026; City of Brisbane, undated)

  2. Orchard Partners announced it had submitted a new plan without the data center, leaving one 892,000-square-foot building for advanced manufacturing. (Orchard Partners, Nov. 5, 2025)

  3. Orchard Partners announced a revised plan with a 180,000-square-foot data center and a second industrial building, about 890,000 sq ft together. (Orchard Partners, July 1, 2025; DatacenterDynamics, July 25, 2025)

  4. Brisbane's Draft EIR for the site described a 1.3 million sq ft warehouse project, not a data center. (CEQAnet (State Clearinghouse), Oct. 7, 2024; City of Brisbane, undated)

Conflicts and open questions

  • Site size is about 153 acres in the city's notice and CEQAnet, and about 144 to 145 acres in developer and press accounts.
  • The size figure is the data center building as proposed in 2025.
  • Opponents raised concerns about endangered butterfly species and other habitat, per DCD; no finding on the merits.
  • The city's page dates the revised submission Nov. 4, 2025; Orchard's release is dated Nov. 5.

The full record

Status note
The developer removed the data center in November 2025, and the city's August 2026 notice says the project includes none. This status covers the data center only: the rest of the project remains under city review.
Power note
No data center power figure was published. The current project's 49.9 MW substation is for a plan with no data center.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.