Data center campus · 2407 and 2408 AK Street, McClellan Business Park, Sacramento County, Sacramento County, California

Prime Data Centers McClellan Park campus (SMF01)

Under construction as of May 7, 2026

Prime has one operating building and a second under construction at McClellan Business Park, 26 MW in all. Also known as: SMF01-01, SMF01-02, SMF02.

Cite← California data centers
Alameda CountyAlpine CountyAmador CountyButte CountyCalaveras CountyColusa CountyContra Costa CountyDel Norte CountyEl Dorado CountyFresno CountyGlenn CountyHumboldt CountyImperial CountyInyo CountyKern CountyKings CountyLake CountyLassen CountyLos Angeles CountyMadera CountyMarin CountyMariposa CountyMendocino CountyMerced CountyModoc CountyMono CountyMonterey CountyNapa CountyNevada CountyOrange CountyPlacer CountyPlumas CountyRiverside CountySacramento CountySan Benito CountySan Bernardino CountySan Diego CountySan Francisco CountySan Joaquin CountySan Luis Obispo CountySan Mateo CountySanta Barbara CountySanta Clara CountySanta Cruz CountyShasta CountySierra CountySiskiyou CountySolano CountySonoma CountyStanislaus CountySutter CountyTehama CountyTrinity CountyTulare CountyTuolumne CountyVentura CountyYolo CountyYuba CountyPrime Data Centers McClellan Park campus (SMF01) · Under construction · 26 MW
Power26MW reported · stated
Floor area215,000sq ft
Site8.64acres
IT load26MW

Who is behind it

ProjectPrime Data Centers McClellan Park campus (SMF01)Also: SMF01-01, SMF01-02, SMF02
Developer and teamPrime Data Centers
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. Prime said it had broken ground on the 18 MW, 150,000-square-foot second building, with SMUD supplying power. (Prime Data Centers, May 7, 2026; Clune Construction, May 12, 2026; Prime Data Centers, undated; DatacenterDynamics, undated)

  2. DCD, crediting the Sacramento Business Journal, reported a pre-application to Sacramento County for a second building; Prime confirmed 18 MW to DCD. (DatacenterDynamics, Jan. 13, 2025)

  3. Prime said it had signed an 8 MW build-to-suit lease on the campus with an unnamed publicly traded tech company. (Prime Data Centers, April 20, 2021)

  4. Prime announced its first building at McClellan Park: 8 MW, about 70,000 sq ft, and ready to occupy. (Prime Data Centers, Jan. 14, 2020)

Conflicts and open questions

  • Abridged by PBS KVIE gives 44 MW for the two-building campus in two reports, and Prime did not respond to its requests in the July report. Prime's own page and DCD give 26 MW (8 plus 18), used here.
  • Addresses conflict. Prime's page puts the operating building at 2407 AK Street and the new one at 2408. DCD's 2026 report and Clune Construction associate 2408 with the existing building or its vicinity, and DCD's 2025 report put the filing at 2407. Coordinates are for the business park, not a matched address.
  • Prime's page gives 8.64 acres for the two buildings. Its 2020 release gave 38 acres for the campus and described several approved buildings; its 2021 release said six were planned and 50 MW was pre-positioned at the substation. No later record of those further buildings was opened.
  • The second building was first announced in November 2021 as 150,000 sq ft and 16 MW, per DCD; the description on Prime's page also still says 16 MW.
  • Prime gives the first building as about 70,000 sq ft in 2020 and 65,000 sq ft on its current page. DCD's 2025 report described the filed second building as about 110,000 sq ft on about 7.74 acres, smaller than the 150,000 sq ft Prime now gives.

The full record

Status note
First building (8 MW) is operating; ground was broken on the second (18 MW) in May 2026, and Prime's page lists it as under construction.
Power note
Critical IT load: 8 MW operating plus 18 MW under construction, per Prime. Under 50 MW.
Evidence
Primary public records
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.