Coachella Valley Technology Campus
A campus planned on farmland in Coachella that the city council ended months after approving its utility agreement.
Who is behind it
The record, newest first
The council approved a permanent ban, Ordinance No. 1231, after a unanimous first reading on Aug. 12. (NBC Palm Springs (City News Service), Aug. 26, 2026; NBC Palm Springs, Aug. 26, 2026; KVCR News, Aug. 28, 2026)
The council unanimously adopted a 45-day moratorium and voted to end the Stronghold agreement and the project. (NBC Palm Springs, June 4, 2026; Patch, June 5, 2026; Palm Springs Tribune, June 8, 2026)
The council voted 4-0 to schedule a special meeting on a pause or permanent ban. (Palm Springs Tribune, June 8, 2026)
The council approved a municipal utility development agreement with Coachella Valley Power Services LLC, a Stronghold affiliate. (Patch, June 5, 2026)
Conflicts and open questions
- Acreage varies: 240 acres with possible growth to 450 (Palm Springs Tribune), at least 240 (Patch), more than 400 (NBC Palm Springs). The 3 million square feet is the Palm Springs Tribune figure for six buildings.
The full record
- Status note
- Denied here means the Coachella City Council itself ended the project on June 4, 2026, voting to terminate the agreement; it adopted a permanent ban on Aug. 26. Stronghold said it would consider its options, and KVCR reported in August that it still opposed the decision.
- Power note
- Reported as 270 to 300 MW, by the Palm Springs Tribune only.
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)