| AlohaNAP | 1547 Critical Systems Realty; Hawaii Pacific Teleport | 1.5 | Operating | July 16, 2026 | Under 50 MW |
| Servpac MTP Data Center | Servpac Inc. | 1 | Operating | March 9, 2026 | Under 50 MW |
| DRFortress Honolulu | DRFortress; 1547 Critical Systems Realty; Harrison Street | — | Operating | March 24, 2026 | Under 50 MW |
| Hawaiian Telcom Endeavor Data Center | Hawaiian Telcom | — | Operating | Oct. 2026 | Under 50 MW |
| Servpac Puahale Data Center | Servpac Inc. | — | Operating | Aug. 28, 2026 | Under 50 MW |
| State of Hawaii Data Center (Kalanimoku Building) | State of Hawaii Office of Enterprise Technology Services | — | Operating | 2024 | Under 50 MW |
| University of Hawaii IT Center Data Center | University of Hawaii | — | Operating | Oct. 2026 | Under 50 MW |
Updates, newest first
- Oct. 2026 Hawaiian Telcom Endeavor Data Center · Hawaiian Telcom markets colocation at Endeavor on its business pages. (Hawaiian Telcom, undated; Hawaiian Telcom, undated; PeeringDB (operator-maintained facility entry), Sept. 26, 2025)
- Aug. 2026 Servpac Puahale Data Center · Servpac's own facility page markets colocation at the site. (Servpac, Aug. 28, 2026; PeeringDB (operator-maintained facility entry), May 20, 2026)
- July 16, 2026 AlohaNAP · 1547 lists the Kapolei site as an active data center, with six network and cloud providers and 1.5 MW of utility power. (1547 Critical Systems Realty, July 16, 2026; 1547 Critical Systems Realty, undated)
- March 24, 2026 DRFortress Honolulu · The operator lists 800 racks for lease in more than 65,000 sq ft. The new owner, 1547, also lists the site in its portfolio. (DRFortress, March 24, 2026; 1547 Critical Systems Realty, July 16, 2026)
- Jan. 22, 2026 Servpac MTP Data Center · Servpac breaks ground on Building 2, a $13 million addition of about 15,500 sq ft that is expected to more than double capacity. (Servpac, Jan. 28, 2026; Building Industry Hawaii, March 9, 2026; Data Center Dynamics, undated)
- April 3, 2025 DRFortress Honolulu · GI Partners sells DRFortress to 1547 Critical Systems Realty and Harrison Street; terms were not disclosed. (Paul, Weiss, April 3, 2025)
- June 27, 2023 Servpac MTP Data Center · Servpac begins an expansion to double colocation capacity, with completion expected in October 2023. (Servpac, June 27, 2023)
- June 22, 2023 State of Hawaii Data Center (Kalanimoku Building) · Civil Beat reports that about 70% of state data has moved to out-of-state servers. Sensitive data such as criminal justice and tax records stays in the basement, and funding to relocate has not been approved. (Honolulu Civil Beat, June 22, 2023)
- 2023 State of Hawaii Data Center (Kalanimoku Building) · The state's data center relocation budget is cut from $5 million to $1 million. (Data Center Dynamics, undated)
- 2023 State of Hawaii Data Center (Kalanimoku Building) · Senate Bill 284 proposes decommissioning the Kalanimoku facility and moving the state's data center to a single standalone site. The bill says the center was created more than 40 years ago. (Hawaii State Legislature, 2024)
- Oct. 2022 DRFortress Honolulu · A fourth expansion is announced, adding about 200 cabinets for a total of 800 and roughly 500 kW of new power, with another 500 kW planned for early 2024. (Data Center Dynamics, undated; Capacity Media, undated)
- Sept. 2021 Servpac MTP Data Center · The first phase is completed. (Data Center Dynamics, undated)
- March 2021 DRFortress Honolulu · The expansion is completed, bringing the campus to about 600 cabinets in 55,000 square feet. (Data Center Dynamics, undated)
- March 2021 Servpac MTP Data Center · Servpac publishes a facility sheet listing 1 MW of available power in the 30,000 sq ft building. (Servpac, undated)
- Aug. 4, 2020 Servpac MTP Data Center · The facility is reported open. (Area Development, Aug. 4, 2020)
- June 16, 2020 DRFortress Honolulu · DRFortress announces its third expansion of the Honolulu campus, adding about 130 cabinets, with service expected in late 2020. (Area Development, June 16, 2020)
- Jan. 17, 2020 Servpac MTP Data Center · Servpac announces the facility as a carrier-neutral data center with disaster recovery office space, and plans to invest $30 million over five years. (Servpac, Jan. 17, 2020)
- Jan. 2020 DRFortress Honolulu · GI Partners takes a majority stake in DRFortress. (Data Center Dynamics, undated)
- Dec. 2019 Servpac MTP Data Center · Servpac buys the 30,000 sq ft data center and disaster recovery facility in Mililani Tech Park. (Servpac, Jan. 24, 2020)
- July 2, 2018 Hawaiian Telcom Endeavor Data Center · Cincinnati Bell completes its acquisition of Hawaiian Telcom. (altafiber (Cincinnati Bell), July 2, 2018)
- Jan. 22, 2018 AlohaNAP · AlohaNAP reports a nearly 70% increase in cabinet capacity and plans a further expansion during 2018. (Total Telecom, Jan. 22, 2018)
- March 15, 2016 University of Hawaii IT Center Data Center · The state technology office signs an agreement to move some state systems into the university data center as a resilient backup. (State of Hawaii Office of Enterprise Technology Services, March 15, 2016)
- March 15, 2016 State of Hawaii Data Center (Kalanimoku Building) · The state signs an agreement to back up some Kalanimoku systems at the University of Hawaii data center. (State of Hawaii Office of Enterprise Technology Services, March 15, 2016)
- 2016 DRFortress Honolulu · Some State of Hawaii IT applications are redirected to a DRFortress facility, according to Data Center Dynamics. (Data Center Dynamics, undated)
- Jan. 20, 2015 AlohaNAP · The redesigned facility, formerly called Hawaii Pacific Data, is reported fully operational as AlohaNAP, a joint venture of 1547 and Hawaii Pacific Teleport, with about 10,000 sq ft of turnkey space. (Data Center Knowledge, Jan. 20, 2015; Data Center Dynamics, undated)
- Dec. 16, 2013 University of Hawaii IT Center Data Center · The building is dedicated. (University of Hawaii Information Technology Services, undated; State of Hawaii Office of Enterprise Technology Services, March 15, 2016)
- Sept. 30, 2013 Hawaiian Telcom Endeavor Data Center · Hawaiian Telcom acquires SystemMetrics, which had a Honolulu data center with about 6,500 sq ft of capacity. (U.S. Securities and Exchange Commission, March 2014)
- Feb. 2, 2012 University of Hawaii IT Center Data Center · Construction begins on the IT Center. (University of Hawaii Information Technology Services, undated)
- 2006 DRFortress Honolulu · DRFortress begins serving Hawaii from its Honolulu facility. (DRFortress, undated; Data Center Dynamics, undated)
Statewide
Data center study (2026): HCR 206 HD1 and HR 196 HD1, adopted in April 2026, ask the Hawaii State Energy Office to convene a working group on how data centers of 5 MW or more would affect utilities, ratepayers, water and climate goals and to report before the 2027 session; the resolution notes Hawaii had not yet received a hyperscale proposal. (Hawaii State Legislature, April 1, 2026; Civil Beat Digital Democracy (legislative status tracker), April 27, 2026; Hawaii State Legislature, April 1, 2026; LegiScan (legislative status tracker), April 9, 2026) The Senate's version, SR 90, was reported out of committee as amended (SD 1) on April 8, 2026, adding study items such as a megawatt threshold for a large data center, on-site backup power that can curtail load in grid emergencies, independently verified energy and water reporting, and ties to the PUC's integrated grid planning; the concurrent SCR 95 SD1 was referred to House committees on April 10. Civil Beat reported the working group first met in September 2026. (Hawaii State Senate, April 8, 2026; Civil Beat Digital Democracy (legislative status tracker), April 8, 2026; Hawaii State Senate, April 9, 2026; LegiScan (legislative status tracker), April 10, 2026; Honolulu Civil Beat, Oct. 7, 2026) Tax credit (not enacted): SB 338 (2025) would have revived the 4% technology infrastructure renovation income-tax credit (HRS 235-110.51) and added data servers to qualifying equipment; it cleared Senate committees in February 2025 and a House committee on March 21, 2025, and has no recorded action since then. (Hawaii State Senate, Feb. 12, 2025; Hawaii House of Representatives, March 21, 2025; Hawaii State Legislature, March 21, 2025; Legiplex (legislative status tracker), March 21, 2025) Hawaii data centers →