Data center campus · 6011 Chapel Hill Road, Raleigh, Wake County, North Carolina
American Tower Raleigh edge data center (RA1)
Operating
as of May 27, 2025
American Tower opened a 4,000-square-foot, 1 MW edge facility at the base of one of its cell towers in Raleigh, sized to grow to 4 MW and 16,000 square feet.
Power1MW reported · stated
Floor area4,000sq ft
Who is behind it
ProjectAmerican Tower Raleigh edge data center (RA1)
Developer and teamAmerican Tower
End userColocation; no tenants named
The record, newest first
Telco Magazine reported the facility open at 1 MW and 4,000 square feet; DatacenterDynamics described a ribbon-cutting and designation RA1. (Telco Magazine, May 27, 2025; DatacenterDynamics, undated; CoreSite, Nov. 2, 2026)
American Tower broke ground on the Raleigh site, aiming to go live in early 2025. (SDxCentral, undated; DatacenterDynamics, undated)
Conflicts and open questions
- CoreSite's listing still uses future-tense language for this site. Trade press reports it open, and American Tower's own page does not state an opening date.
- The June 2024 groundbreaking date is derived from DatacenterDynamics' undated reference to June of the prior year.
- Under 50 MW.
The full record
- Power note
- Trade press reports 1 MW at opening. American Tower's page states up to 4 MW-plus of usable IT power at full size and gives no opening figure.
- Evidence
- Primary public records
- Size class