Data center campus · Undisclosed industrial park, Cumberland County, Cumberland County, North Carolina

PRSM Group client data center, Cumberland County

Proposed as of May 18, 2026

A Virginia firm told Cumberland County commissioners that an unnamed client wants a 225 MW AI data center on about 50 acres in an industrial park it did not identify.

Cite← North Carolina data centers
Alamance CountyAlexander CountyAlleghany CountyAnson CountyAshe CountyAvery CountyBeaufort CountyBertie CountyBladen CountyBrunswick CountyBuncombe CountyBurke CountyCabarrus CountyCaldwell CountyCamden CountyCarteret CountyCaswell CountyCatawba CountyChatham CountyCherokee CountyChowan CountyClay CountyCleveland CountyColumbus CountyCraven CountyCumberland CountyCurrituck CountyDare CountyDavidson CountyDavie CountyDuplin CountyDurham CountyEdgecombe CountyForsyth CountyFranklin CountyGaston CountyGates CountyGraham CountyGranville CountyGreene CountyGuilford CountyHalifax CountyHarnett CountyHaywood CountyHenderson CountyHertford CountyHoke CountyHyde CountyIredell CountyJackson CountyJohnston CountyJones CountyLee CountyLenoir CountyLincoln CountyMacon CountyMadison CountyMartin CountyMcDowell CountyMecklenburg CountyMitchell CountyMontgomery CountyMoore CountyNash CountyNew Hanover CountyNorthampton CountyOnslow CountyOrange CountyPamlico CountyPasquotank CountyPender CountyPerquimans CountyPerson CountyPitt CountyPolk CountyRandolph CountyRichmond CountyRobeson CountyRockingham CountyRowan CountyRutherford CountySampson CountyScotland CountyStanly CountyStokes CountySurry CountySwain CountyTransylvania CountyTyrrell CountyUnion CountyVance CountyWake CountyWarren CountyWashington CountyWatauga CountyWayne CountyWilkes CountyWilson CountyYadkin CountyYancey CountyPRSM Group client data center, Cumberland County · Proposed · 225 MW
Power225MW reported · stated
Floor area2,000,000sq ft
Site50acres

Who is behind it

ProjectPRSM Group client data center, Cumberland County
Developer and teamPRSM Group (for an unnamed client)
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. CityView reported the county later imposed a six-month moratorium that runs to Dec. 15, 2026, with an ordinance due before commissioners in November. (CityView, Oct. 30, 2026)

  2. At the county's moratorium hearing, a PRSM Group partner described two 1 million-square-foot stages, 15 to 18 months of building and about 1,500 construction jobs, and said he hoped commissioners would not adopt a pause; no vote was taken. (CityView, May 21, 2026)

Conflicts and open questions

  • Site not identified; coordinates are Fayetteville and only mark the county.

The full record

Status note
Described at a public hearing only; its representative did not expect it to move before a moratorium.
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.