Data center campus · 3101 International Airport Drive, Charlotte, Mecklenburg County, North Carolina
Segra Charlotte 2 data center, International Airport Drive
Operating
as of Nov. 2024
Segra's Charlotte 2 site, opened in 2012, has 28,000 square feet and 2.5 MW of power capacity, and added a data hall in 2024. Also known as: Charlotte Two Data Center.
Power2.5MW reported · stated
Floor area28,000sq ft
Who is behind it
ProjectSegra Charlotte 2 data center, International Airport DriveAlso: Charlotte Two Data Center
Developer and teamSegra
End userNot found in the recordsNot yet named in any record or credited report we have found.
The record, newest first
Segra's site sheet, in a November 2024 upload folder, says the 28,000-square-foot center at 3101 International Airport Drive opened in 2012 and added a data hall in 2024, with 2.5 MW of power capacity. (Segra, undated)
DatacenterDynamics reported Segra had finished expanding what it called a $10 million data center, doubling it to 14,000 square feet. (DatacenterDynamics, June 26, 2024)
Conflicts and open questions
- Size differs by measure: 28,000 sq ft for the facility and 14,032 sq ft of data center floor (Segra); DatacenterDynamics' 14,000 sq ft matches the floor figure.
- DatacenterDynamics describes $10 million as the data center's value and does not separately price the expansion.
- Segra's 1612 Cross Beam Drive site was reported available for sale or lease, with Segra moving out; it is not included here.
The full record
- Power note
- 2.5 MW power capacity per Segra's site sheet, which does not break it into utility or critical load.
- Evidence
- Primary public records
- Size class
- Under 50 MW (outside main scope; kept for completeness)