Data center campus · Custer Avenue near the Fayetteville PWC power plant and Eastover, Cumberland County, North Carolina

Terra Nexus Custer Avenue data center

Proposed as of Aug. 7, 2026

A Charlotte investment firm proposed a 200 to 300 MW data center on 180 acres near Eastover, whose town council objected in a letter to Fayetteville.

Cite← North Carolina data centers
Alamance CountyAlexander CountyAlleghany CountyAnson CountyAshe CountyAvery CountyBeaufort CountyBertie CountyBladen CountyBrunswick CountyBuncombe CountyBurke CountyCabarrus CountyCaldwell CountyCamden CountyCarteret CountyCaswell CountyCatawba CountyChatham CountyCherokee CountyChowan CountyClay CountyCleveland CountyColumbus CountyCraven CountyCumberland CountyCurrituck CountyDare CountyDavidson CountyDavie CountyDuplin CountyDurham CountyEdgecombe CountyForsyth CountyFranklin CountyGaston CountyGates CountyGraham CountyGranville CountyGreene CountyGuilford CountyHalifax CountyHarnett CountyHaywood CountyHenderson CountyHertford CountyHoke CountyHyde CountyIredell CountyJackson CountyJohnston CountyJones CountyLee CountyLenoir CountyLincoln CountyMacon CountyMadison CountyMartin CountyMcDowell CountyMecklenburg CountyMitchell CountyMontgomery CountyMoore CountyNash CountyNew Hanover CountyNorthampton CountyOnslow CountyOrange CountyPamlico CountyPasquotank CountyPender CountyPerquimans CountyPerson CountyPitt CountyPolk CountyRandolph CountyRichmond CountyRobeson CountyRockingham CountyRowan CountyRutherford CountySampson CountyScotland CountyStanly CountyStokes CountySurry CountySwain CountyTransylvania CountyTyrrell CountyUnion CountyVance CountyWake CountyWarren CountyWashington CountyWatauga CountyWayne CountyWilkes CountyWilson CountyYadkin CountyYancey CountyTerra Nexus Custer Avenue data center · Proposed · 300 MW
Power300MW reported · stated
Site180acres

Who is behind it

ProjectTerra Nexus Custer Avenue data center
Developer and teamTerra Nexus Ventures
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. CityView reported the site is outside city limits and under 4,000 feet from Eastover, and that the developer has proposed annexation; no annexation decision was reported. (CityView, Aug. 7, 2026)

  2. Eastover's town attorney wrote to the City of Fayetteville on behalf of the town council, objecting to satellite annexations for such projects. (Town of Eastover, July 15, 2026)

  3. CityView described the plans submitted to Fayetteville as 300 MW. (CityView, May 21, 2026)

  4. CityView reported the 180-acre plan by Terra Nexus Ventures near the PWC plant; the firm could not be reached. (CityView, Jan. 27, 2026)

  5. A preapplication for a large data center on Custer Road was filed with the City of Fayetteville, according to Eastover's town attorney. (Town of Eastover, July 15, 2026)

Conflicts and open questions

  • The letter says Custer Road and CityView says Custer Avenue; the letter places the land in unincorporated Cumberland County.
  • The land is outside Fayetteville's city limits and annexation has been proposed, so whether the county moratorium through Dec. 15, 2026 or a city rule would apply is not settled in the sources opened.
  • Coordinates are approximate, from Eastover.

The full record

Status note
A preapplication was filed in September 2025 and the developer has proposed annexation; no later filing or vote was found.
Power note
CityView reported 200 MW in January 2026 and 300 MW in May 2026.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)