Data center campus · 5301 Departure Drive, Raleigh, Wake County, North Carolina

TierPoint Raleigh data center

Operating as of Nov. 2, 2026

TierPoint's Raleigh colocation site on Departure Drive has about 65,000 square feet of data center space.

Cite← North Carolina data centers
Alamance CountyAlexander CountyAlleghany CountyAnson CountyAshe CountyAvery CountyBeaufort CountyBertie CountyBladen CountyBrunswick CountyBuncombe CountyBurke CountyCabarrus CountyCaldwell CountyCamden CountyCarteret CountyCaswell CountyCatawba CountyChatham CountyCherokee CountyChowan CountyClay CountyCleveland CountyColumbus CountyCraven CountyCumberland CountyCurrituck CountyDare CountyDavidson CountyDavie CountyDuplin CountyDurham CountyEdgecombe CountyForsyth CountyFranklin CountyGaston CountyGates CountyGraham CountyGranville CountyGreene CountyGuilford CountyHalifax CountyHarnett CountyHaywood CountyHenderson CountyHertford CountyHoke CountyHyde CountyIredell CountyJackson CountyJohnston CountyJones CountyLee CountyLenoir CountyLincoln CountyMacon CountyMadison CountyMartin CountyMcDowell CountyMecklenburg CountyMitchell CountyMontgomery CountyMoore CountyNash CountyNew Hanover CountyNorthampton CountyOnslow CountyOrange CountyPamlico CountyPasquotank CountyPender CountyPerquimans CountyPerson CountyPitt CountyPolk CountyRandolph CountyRichmond CountyRobeson CountyRockingham CountyRowan CountyRutherford CountySampson CountyScotland CountyStanly CountyStokes CountySurry CountySwain CountyTransylvania CountyTyrrell CountyUnion CountyVance CountyWake CountyWarren CountyWashington CountyWatauga CountyWayne CountyWilkes CountyWilson CountyYadkin CountyYancey CountyTierPoint Raleigh data center · Operating
PowerNot statedNot reported in the records found
Floor area65,000sq ft

Who is behind it

ProjectTierPoint Raleigh data center
Developer and teamTierPoint
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. TierPoint lists 5301 Departure Drive as a current data center with about 65,000 square feet. (TierPoint, Nov. 2, 2026; TierPoint, undated; TierPoint, undated)

Conflicts and open questions

  • TierPoint's production space figure differs: more than 40,000 sq ft of raised floor on its web page, more than 33,000 sq ft gross on its spec sheet.

The full record

Power note
No load figure from TierPoint. Its five 2 MW generators are backup, and its five 2,500 kVA transformers are equipment ratings, not demand.
Evidence
Primary public records
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.