A 25,600-square-foot 365 Data Centers colocation site in Bridgewater.
Power2.3MW reported · stated
Floor area25,600sq ft
Who is behind it
Project365 Data Centers Bridgewater
Developer and team365 Data Centers
End userNot found in the recordsNot yet named in any record or credited report we have found.
The record, newest first
The operator's page, last changed on this date, listed 25,600 square feet and 2.3 MW, with 20 MW available for future expansion. (365 Data Centers, May 22, 2025)
Conflicts and open questions
- Coordinates are approximate, from the operator's address.
The full record
- Status note
- Live on the operator's site in November 2026, offered for colocation and tours; the page was last changed in May 2025.
- Power note
- 2.3 MW now, with the operator saying 20 MW in total is available for future expansion. Under 50 MW.
- Evidence
- Primary public records
- Size class
- Under 50 MW (outside main scope; kept for completeness)