Data center campus · 101 Possumtown Road, Piscataway, Middlesex County, New Jersey

QTS Piscataway campus (Piscataway 1)

Operating as of July 2026

QTS's 38-acre Piscataway site, bought from DuPont Fabros in 2016, with an added two-story expansion listed on its page. Also known as: Piscataway 1, PNJ1.

Cite← New Jersey data centers
Atlantic CountyBergen CountyBurlington CountyCamden CountyCape May CountyCumberland CountyEssex CountyGloucester CountyHudson CountyHunterdon CountyMercer CountyMiddlesex CountyMonmouth CountyMorris CountyOcean CountyPassaic CountySalem CountySomerset CountySussex CountyUnion CountyWarren CountyQTS Piscataway campus (Piscataway 1) · Operating · 65 MW
Power65MW reported · stated
Floor area360,000sq ft
Site38acres
IT load65MW

Who is behind it

ProjectQTS Piscataway campus (Piscataway 1)Also: Piscataway 1, PNJ1
Developer and teamQTS Data Centers (through QTS Investment Properties Piscataway, LLC)
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. A Colocation Scout permit review reported a pending air permit change at the address and a generator permit approved June 6, 2024. (Colocation Scout, Oct. 13, 2026)

  2. QTS's page, last changed on this date, listed 65 MW or more of critical capacity and an additional two-story, 50,000-square-foot, 15 MW expansion. (QTS Data Centers, July 1, 2026)

  3. QTS sought site plan approval for a two-story addition of about 45,000 square feet a floor, with a planning board hearing set for Feb. 9. (DatacenterDynamics, 2022; MyCentralJersey.com, via AOL, undated)

  4. QTS bought the 360,000-square-foot campus from DuPont Fabros Technology for $125 million, DCD reported. (DatacenterDynamics, 2022)

Conflicts and open questions

  • The year of the hearing is inferred from DCD's statement that Blackstone bought QTS the year before; neither article shows a date in the text read.
  • The outcome of the 2022 hearing was not found; Piscataway's minutes links do not load.
  • The square footage dates from the 2016 sale.
  • Coordinates are approximate, from the operator's address.

The full record

Status note
QTS's page lists the 38-acre site with 65 MW or more of critical capacity and a further 15 MW expansion, without saying what stage the expansion has reached.
Power note
65 MW or more of critical capacity on the QTS page last changed July 1, 2026; DCD gave up to 52 MW at the time of the 2022 filing.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.