QTS Piscataway campus (Piscataway 1)
QTS's 38-acre Piscataway site, bought from DuPont Fabros in 2016, with an added two-story expansion listed on its page. Also known as: Piscataway 1, PNJ1.
Who is behind it
The record, newest first
A Colocation Scout permit review reported a pending air permit change at the address and a generator permit approved June 6, 2024. (Colocation Scout, Oct. 13, 2026)
QTS's page, last changed on this date, listed 65 MW or more of critical capacity and an additional two-story, 50,000-square-foot, 15 MW expansion. (QTS Data Centers, July 1, 2026)
QTS sought site plan approval for a two-story addition of about 45,000 square feet a floor, with a planning board hearing set for Feb. 9. (DatacenterDynamics, 2022; MyCentralJersey.com, via AOL, undated)
QTS bought the 360,000-square-foot campus from DuPont Fabros Technology for $125 million, DCD reported. (DatacenterDynamics, 2022)
Conflicts and open questions
- The year of the hearing is inferred from DCD's statement that Blackstone bought QTS the year before; neither article shows a date in the text read.
- The outcome of the 2022 hearing was not found; Piscataway's minutes links do not load.
- The square footage dates from the 2016 sale.
- Coordinates are approximate, from the operator's address.
The full record
- Status note
- QTS's page lists the 38-acre site with 65 MW or more of critical capacity and a further 15 MW expansion, without saying what stage the expansion has reached.
- Power note
- 65 MW or more of critical capacity on the QTS page last changed July 1, 2026; DCD gave up to 52 MW at the time of the 2022 filing.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)