Data center campus · Rainbow Road off Highway 421, Mountain City, Johnson County, Tennessee

CleanSpark Mountain City bitcoin facility

Denied as of Aug. 12, 2025

A 30 MW bitcoin mine that lost its rezoning in Mountain City in 2025, after which a Johnson County measure to gain power over such businesses also failed.

Cite← Tennessee data centers
Anderson CountyBedford CountyBenton CountyBledsoe CountyBlount CountyBradley CountyCampbell CountyCannon CountyCarroll CountyCarter CountyCheatham CountyChester CountyClaiborne CountyClay CountyCocke CountyCoffee CountyCrockett CountyCumberland CountyDavidson CountyDecatur CountyDeKalb CountyDickson CountyDyer CountyFayette CountyFentress CountyFranklin CountyGibson CountyGiles CountyGrainger CountyGreene CountyGrundy CountyHamblen CountyHamilton CountyHancock CountyHardeman CountyHardin CountyHawkins CountyHaywood CountyHenderson CountyHenry CountyHickman CountyHouston CountyHumphreys CountyJackson CountyJefferson CountyJohnson CountyKnox CountyLake CountyLauderdale CountyLawrence CountyLewis CountyLincoln CountyLoudon CountyMacon CountyMadison CountyMarion CountyMarshall CountyMaury CountyMcMinn CountyMcNairy CountyMeigs CountyMonroe CountyMontgomery CountyMoore CountyMorgan CountyObion CountyOverton CountyPerry CountyPickett CountyPolk CountyPutnam CountyRhea CountyRoane CountyRobertson CountyRutherford CountyScott CountySequatchie CountySevier CountyShelby CountySmith CountyStewart CountySullivan CountySumner CountyTipton CountyTrousdale CountyUnicoi CountyUnion CountyVan Buren CountyWarren CountyWashington CountyWayne CountyWeakley CountyWhite CountyWilliamson CountyWilson CountyCleanSpark Mountain City bitcoin facility · Denied · 30 MW
Power30MW reported · stated
Site50acres

Who is behind it

ProjectCleanSpark Mountain City bitcoin facility
Developer and teamCleanSpark
End userCleanSpark

The record, newest first

  1. A Johnson County measure to adopt the County Powers Act, which would have let the commission restrict businesses including crypto mines and data centers, failed on a 7-6 split with two absent; WUOT did not explain why seven yes votes were not enough. (WUOT, Aug. 22, 2025)

  2. Mountain City's rezoning of a 50-acre parcel from B-3 to B-4 had passed first reading 3-1 and died at second reading without a motion. (Yahoo News, undated; SuperTalk 92.9, Aug. 13, 2025; WUOT (via WPLN News), Aug. 19, 2025)

Conflicts and open questions

  • The Aug. 12 date is inferred from stories published Aug. 13 and Aug. 19 that say Tuesday. Coordinates are approximate, from the reported road and town.

The full record

Status note
The rezoning failed at second reading when nobody moved to approve it.
Power note
Under 50 MW. A bitcoin mine, kept because local rules treat these with data centers.
Evidence
News reports; primary records not yet obtained
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.