Data center campus · 1398 Gateway Drive, Gallatin, Sumner County, Tennessee

Centersquare (Evoque) Gallatin campus

Proposed as of June 12, 2026

A planned four-phase data center campus of more than 100 MW on 61 acres in Gallatin, near but separate from Meta's campus, announced by Evoque and Archer Datacenters in 2022 and now carried under the Centersquare name. Also known as: Evoque Nashville, Csquare Nashville, Archer Gallatin.

Cite← Tennessee data centers
Anderson CountyBedford CountyBenton CountyBledsoe CountyBlount CountyBradley CountyCampbell CountyCannon CountyCarroll CountyCarter CountyCheatham CountyChester CountyClaiborne CountyClay CountyCocke CountyCoffee CountyCrockett CountyCumberland CountyDavidson CountyDecatur CountyDeKalb CountyDickson CountyDyer CountyFayette CountyFentress CountyFranklin CountyGibson CountyGiles CountyGrainger CountyGreene CountyGrundy CountyHamblen CountyHamilton CountyHancock CountyHardeman CountyHardin CountyHawkins CountyHaywood CountyHenderson CountyHenry CountyHickman CountyHouston CountyHumphreys CountyJackson CountyJefferson CountyJohnson CountyKnox CountyLake CountyLauderdale CountyLawrence CountyLewis CountyLincoln CountyLoudon CountyMacon CountyMadison CountyMarion CountyMarshall CountyMaury CountyMcMinn CountyMcNairy CountyMeigs CountyMonroe CountyMontgomery CountyMoore CountyMorgan CountyObion CountyOverton CountyPerry CountyPickett CountyPolk CountyPutnam CountyRhea CountyRoane CountyRobertson CountyRutherford CountyScott CountySequatchie CountySevier CountyShelby CountySmith CountyStewart CountySullivan CountySumner CountyTipton CountyTrousdale CountyUnicoi CountyUnion CountyVan Buren CountyWarren CountyWashington CountyWayne CountyWeakley CountyWhite CountyWilliamson CountyWilson CountyCentersquare (Evoque) Gallatin campus · Proposed · 100 MW
Power100MW reported · stated
Floor area500,000sq ft
Site61acres

Who is behind it

ProjectCentersquare (Evoque) Gallatin campusAlso: Evoque Nashville, Csquare Nashville, Archer Gallatin
Developer and teamCentersquare (formerly Evoque Data Center Solutions, Brookfield)
Archer Datacenters
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. NewsChannel 5 listed an 82,000-square-foot first phase among existing facilities and a planned 500,000-square-foot campus. (NewsChannel 5 (WTVF), June 12, 2026)

  2. WSMV listed Csquare's 1398 Gateway Drive site among proposed, not yet built, Nashville-area data centers. (WSMV, June 4, 2026)

  3. Evoque and Archer Datacenters announced a joint venture to expand Archer's 28.5-acre site, which had an 82,000-square-foot shell, by adding a 32.8-acre parcel, for more than 500,000 square feet in four phases. (Evoque Data Center Solutions (GlobeNewswire), May 12, 2022; Bisnow, May 16, 2022)

Conflicts and open questions

  • This is not Meta's campus: Bisnow and Evoque's release describe Meta's site as next door. Meta buildings do not belong under this project.
  • Status conflict among directories: Baxtel lists it as operational (built 2024) while also saying Centersquare is developing the campus; datacenterHawk says not yet commissioned or leased, and a second building planned; Data Center Map says under construction; Datacenters.com says Archer's page shows the location as exited. None is a public record, so WSMV's and NewsChannel 5's June 2026 lists control.
  • No Gallatin planning record for this campus was found.
  • The Evoque-to-Centersquare name change is from Baxtel's company history; WSMV uses Csquare at the same address.
  • Coordinates are approximate, placed near Meta's campus because reports describe the two as neighbors; the street address could not be geocoded here.

The full record

Status note
An 82,000-square-foot first-phase shell exists; the wider campus remains planned, and sources disagree on whether the shell is in service.
Power note
Evoque's 2022 figure for full build-out (over 100 MW), of which over 40 MW was available then; growth past that depended on Gallatin Department of Electricity and TVA transmission capacity.