Data center campus · 1496 Highway 66, next to a fractionation plant, Bulls Gap, Hawkins County, Tennessee

ExoticRidge Bulls Gap bitcoin mine

Paused by moratorium as of July 28, 2026

An 8 MW bitcoin mine at the center of a federal civil rights suit over Hawkins County's ban on data centers and crypto mines.

Cite← Tennessee data centers
Anderson CountyBedford CountyBenton CountyBledsoe CountyBlount CountyBradley CountyCampbell CountyCannon CountyCarroll CountyCarter CountyCheatham CountyChester CountyClaiborne CountyClay CountyCocke CountyCoffee CountyCrockett CountyCumberland CountyDavidson CountyDecatur CountyDeKalb CountyDickson CountyDyer CountyFayette CountyFentress CountyFranklin CountyGibson CountyGiles CountyGrainger CountyGreene CountyGrundy CountyHamblen CountyHamilton CountyHancock CountyHardeman CountyHardin CountyHawkins CountyHaywood CountyHenderson CountyHenry CountyHickman CountyHouston CountyHumphreys CountyJackson CountyJefferson CountyJohnson CountyKnox CountyLake CountyLauderdale CountyLawrence CountyLewis CountyLincoln CountyLoudon CountyMacon CountyMadison CountyMarion CountyMarshall CountyMaury CountyMcMinn CountyMcNairy CountyMeigs CountyMonroe CountyMontgomery CountyMoore CountyMorgan CountyObion CountyOverton CountyPerry CountyPickett CountyPolk CountyPutnam CountyRhea CountyRoane CountyRobertson CountyRutherford CountyScott CountySequatchie CountySevier CountyShelby CountySmith CountyStewart CountySullivan CountySumner CountyTipton CountyTrousdale CountyUnicoi CountyUnion CountyVan Buren CountyWarren CountyWashington CountyWayne CountyWeakley CountyWhite CountyWilliamson CountyWilson CountyExoticRidge Bulls Gap bitcoin mine · Paused by moratorium · 8 MW
Power8MW reported · stated

Who is behind it

ProjectExoticRidge Bulls Gap bitcoin mine
Developer and teamExoticRidge Crypto Company LLC
End userExoticRidge

The record, newest first

  1. Commissioners passed a further ban resolution with 12 yes votes and two absent. (WATE (WJHL), July 28, 2026)

  2. The Beacon Center of Tennessee sued for ExoticRidge in the Eastern District of Tennessee, alleging the ban is unconstitutional and arbitrary. No ruling was found. (Data Center Dynamics, undated; WUOT (via WPLN News), April 13, 2026)

  3. A proposed settlement letting the company build died before the commission for lack of a second. The company had said it received state construction permits for its generators in January. (WJHL, Feb. 24, 2026; WJHL, Feb. 21, 2026)

  4. Hawkins County's commission passed a resolution banning data centers and crypto mines, 10-2 per WJHL. (Data Center Dynamics, undated; WUOT (via WPLN News), April 13, 2026; WJHL, May 19, 2026)

Conflicts and open questions

  • The complaint itself was not opened; claims come from reporting and are the company's allegations.
  • Filing date conflict: DCD says March 31, while WJHL's May 19 story says the suit was filed the month before.
  • Coordinates are approximate, from the town.

The full record

Status note
Blocked by Hawkins County's ban, which the company is challenging in federal court. WJHL said in February 2026 that construction had not started.
Power note
Under 50 MW. A bitcoin mine; the company says it would generate its own power from adjacent ethane.
Evidence
News reports; primary records not yet obtained
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.