Data center campus · Two blocks in Downtown Memphis near FedExForum, Beale Street and AutoZone Park, Shelby County, Tennessee
Neural Nexus innovation district (not confirmed as a data center)
Proposed
as of Dec. 18, 2025
Not confirmed as a data center: a mixed-use downtown district with an unsized sovereign cloud computing portion, announced at a Memphis Chamber lunch in December 2025; its CEO says it is not a data center. Also known as: The Walk on Union site.
PowerNot statedNot reported in the records found
Floor area1,742,400sq ft
Who is behind it
ProjectNeural Nexus innovation district (not confirmed as a data center)Also: The Walk on Union site
Developer and teamLegacy Power Capital
End userNot found in the recordsNot yet named in any record or credited report we have found.
The record, newest first
Legacy Power Capital announced the district at the Memphis Chamber's annual lunch. Neural Nexus CEO Rob Miller said it is not a data center; chamber leaders called it a cloud computing center. (WMC Action News 5, Dec. 10, 2025; Downtown Memphis Commission, undated; WREG (via We Are Memphis), Dec. 18, 2025)
Conflicts and open questions
- Whether this counts as a data center is contested by its own backer; the 1.74 million square feet covers the entire project, and the computing share is not given.
- Coordinates are approximate, from the reported blocks.
The full record
- Status note
- Not confirmed as a data center. Announced December 2025 with no timeline or approvals reported in what we opened, and we found no record after that month.
- Power note
- WREG, as carried by We Are Memphis, says the project would be powered by about 70 MW; no source opened ties that to the computing portion or gives a computing size.
- Evidence
- Unconfirmed: a single third-party source
- Size class
- Under 50 MW (outside main scope; kept for completeness)