Oak Ridge Reservation AI data center sites (U.S. Department of Energy)
Two federal tracts totaling about 245 acres that DOE offered for privately funded AI data centers in 2025, then set aside in 2026 when it turned down the proposals for now. Also known as: East Tennessee Technology Park site, Bethel Valley Road site.
Who is behind it
The record, newest first
Hellbender Press reported DOE was declining the Oak Ridge proposals for now. It gave the sites as 95 acres near the lab and 150 acres at the technology park, 83 of them within the Manhattan Project park. (Hellbender Press, Sept. 5, 2026)
DOE requested proposals for two sites, with an industry day on Oct. 15 and a Dec. 1, 2025 deadline. (U.S. Department of Energy, Sept. 30, 2025)
Roane County relayed DOE's selection of the reservation as one of four federal sites for AI data centers and energy projects. (Roane County, July 24, 2025)
Conflicts and open questions
- County follows the Roane County notice. The reservation spans Roane and Anderson counties, and the county of each site was not checked.
- Hellbender's page shows an Aug. 26 header date and says it was updated Sept. 5 and modified Sept. 8, 2026.
- Coordinates are approximate, from the reported location.
The full record
- Status note
- DOE offered the land and took proposals, then declined the Oak Ridge proposals for now to focus on Portsmouth and Paducah. A DOE spokesman says no decision has been made on whether future Oak Ridge missions include large data centers.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)