Data center campus · 2902 and 2906 Brick Church Pike, Trinity Hills, north Nashville, Davidson County, Tennessee

RadiusDC Nashville I

Under construction as of Aug. 25, 2026

A 12 MW colocation building under construction in Nashville's Trinity Hills area, across from a school, where neighbors have raised concerns about water, noise and air even as the city restricts new data centers. Also known as: Nashville I.

Cite← Tennessee data centers
Anderson CountyBedford CountyBenton CountyBledsoe CountyBlount CountyBradley CountyCampbell CountyCannon CountyCarroll CountyCarter CountyCheatham CountyChester CountyClaiborne CountyClay CountyCocke CountyCoffee CountyCrockett CountyCumberland CountyDavidson CountyDecatur CountyDeKalb CountyDickson CountyDyer CountyFayette CountyFentress CountyFranklin CountyGibson CountyGiles CountyGrainger CountyGreene CountyGrundy CountyHamblen CountyHamilton CountyHancock CountyHardeman CountyHardin CountyHawkins CountyHaywood CountyHenderson CountyHenry CountyHickman CountyHouston CountyHumphreys CountyJackson CountyJefferson CountyJohnson CountyKnox CountyLake CountyLauderdale CountyLawrence CountyLewis CountyLincoln CountyLoudon CountyMacon CountyMadison CountyMarion CountyMarshall CountyMaury CountyMcMinn CountyMcNairy CountyMeigs CountyMonroe CountyMontgomery CountyMoore CountyMorgan CountyObion CountyOverton CountyPerry CountyPickett CountyPolk CountyPutnam CountyRhea CountyRoane CountyRobertson CountyRutherford CountyScott CountySequatchie CountySevier CountyShelby CountySmith CountyStewart CountySullivan CountySumner CountyTipton CountyTrousdale CountyUnicoi CountyUnion CountyVan Buren CountyWarren CountyWashington CountyWayne CountyWeakley CountyWhite CountyWilliamson CountyWilson CountyRadiusDC Nashville I · Under construction · 12 MW
Power12MW reported · stated
Floor area102,500sq ft
Site12acres
IT load12MW

Who is behind it

ProjectRadiusDC Nashville IAlso: Nashville I
Developer and teamRadiusDC (backed by Blue Owl Capital)
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. At a community meeting RadiusDC put water use at about 700 gallons a day, said NES and TVA studies found no grid problems, and said diesel backup generators are for emergencies only. (WKRN News 2, Aug. 25, 2026)

  2. Metro Council adopted citywide limits and a moratorium through December on new data center construction. The report does not mention this project or say how the rules apply to it. (WSMV, July 21, 2026)

  3. NewsChannel 5 reported residents' worries over water, sewer, noise and past landfill problems in the area; RadiusDC said it went through Metro's rezoning and permitting and has all required approvals. (NewsChannel 5 (WTVF), July 20, 2026)

  4. WKRN reported that neighbors questioned the project as land clearing began; a nearby barbershop owner said he believed the site was picked because residents are Black. Developers said the project would bring jobs and investment. (WKRN News 2, Sept. 23, 2025)

  5. RadiusDC held its groundbreaking. (Data Center Dynamics, undated; WKRN News 2, Aug. 25, 2026)

  6. RadiusDC announced the facility: 12 MW and 102,500 square feet on about 12 acres, with leasing from the second half of 2025 and opening in 2026. (RadiusDC (PR Newswire, via The Astorian), March 6, 2025; Data Center Dynamics, undated)

  7. Metro approved the site's rezoning, according to WKRN (month only). (WKRN News 2, Aug. 25, 2026)

Conflicts and open questions

  • Status conflict: NewsChannel 5 (June 2026) listed it among existing data centers and WSMV (June 2026) among confirmed ones; WKRN (Aug. 2026) says under construction. The latest report controls.
  • The school across the street is called elementary by WKRN and Richard Dinkins Middle School by NewsChannel 5.
  • The Metro rezoning ordinance itself was not found; the Feb. 2025 date is from WKRN and RadiusDC's account is unverified by NewsChannel 5.
  • RadiusDC's own Nashville page was not opened, so the operator's facts come from its press release and from reporting.
  • Coordinates are approximate, from the Trinity Hills area; the street address could not be geocoded here.

The full record

Status note
Still being built in Aug. 2026; a July 2026 report said it was close to completion.
Power note
Critical power per RadiusDC. Under 50 MW.
Evidence
Primary public records
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.