Data center campus · 8432 Flippo Drive, south of Fredericksburg and east of I-95, Spotsylvania, Virginia
Amazon Carter's Store Tech Campus
Approved
as of Oct. 30, 2025
A 314-acre Amazon campus planned for about 2.6 million sq ft of data centers in phases through 2035, rezoned from rural to industrial in 2023.
PowerNot statedNot reported in the records found
Floor area2,600,000sq ft
Site314acres
Who is behind it
ProjectAmazon Carter's Store Tech Campus
Developer and teamAmazon Data Services
End userAmazon Web Services
The record, newest first
A traffic analysis in a neighboring filing listed the campus as approved and not yet constructed. (Spotsylvania County (applicant narrative, File No. R25-0003), Oct. 30, 2025)
DCD reported the rezoning had been approved. (DatacenterDynamics, Oct. 30, 2023)
Amazon filed to rezone about 314 acres from rural to light industrial for about 2.6 million sq ft of data centers and a substation, phased through 2035. (DatacenterDynamics, undated; Data Center Frontier, June 2, 2023)
Conflicts and open questions
- Acreage is 313 (Data Center Frontier) or 314 (DCD).
- Borders the Summit Crossing campus, per Data Center Frontier.
The full record
- Status note
- Described in an October 2025 county filing as approved but not yet built.
- Power note
- No power figure appears in the sources opened.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)