Data center campus · Ringgold, Pittsylvania, Virginia
58 East Data Campus
Approved
as of Nov. 2024
Anchorstone won a heavy-industrial rezoning and a special use permit in 2024 for a data center campus on about 946 acres south of Route 58 east of Danville.
PowerNot statedNot reported in the records found
Site946acres
Who is behind it
Project58 East Data Campus
Developer and teamAnchorstone Advisors
End userNot found in the recordsNot yet named in any record or credited report we have found.
The record, newest first
The Board of Zoning Appeals unanimously approved the special use permit with 11 proffers. (Showcase Magazine, Nov. 15, 2024)
Planning commission unanimously recommended the special use permit. (Showcase Magazine, Oct. 2, 2024)
Supervisors voted unanimously to rezone the tract for heavy industry. (Virginia Business, Sept. 29, 2024)
Developer applied for a land-use change, heavy industrial rezoning and special use permit for more than 900 acres. (Showcase Magazine, June 3, 2024)
Conflicts and open questions
- Investment figures differ: Virginia Business reported more than $1 billion, Showcase Magazine $4 to $5 billion.
- Coordinates approximate, south of US 58 just east of the Danville line.
- Exact BZA vote date not given in the source (article dated Nov. 15, 2024).
The full record
- Status note
- Rezoning (July 2024) and special use permit (November 2024) approved; no tenant announced and no later public record found in this pass.
- Power note
- Not reported.
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)