Data center campus · 1175 North Main Street, Harrisonburg, Harrisonburg, Virginia

Harrisonburg data center, 1175 North Main Street

Operating as of Feb. 13, 2023

A 100,000-square-foot data center in a converted former Tyco building on North Main Street in Harrisonburg, leased in full to Anthem Health; under 50 MW. Also known as: Cyber Integration Center, DBT-Data Cyber Integration Center, former Tyco building.

Cite← Virginia data centers
AccomackAlbemarleAlexandriaAlleghanyAmeliaAmherstAppomattoxArlingtonAugustaBathBedfordBlandBotetourtBristolBrunswickBuchananBuckinghamBuena VistaCampbellCarolineCarrollCharles CityCharlotteCharlottesvilleChesapeakeChesterfieldClarkeColonial HeightsCovingtonCraigCulpeperCumberlandDanvilleDickensonDinwiddieEmporiaEssexFairfaxFairfax (city)Falls ChurchFauquierFloydFluvannaFranklinFranklin (city)FrederickFredericksburgGalaxGilesGloucesterGoochlandGraysonGreeneGreensvilleHalifaxHamptonHanoverHarrisonburgHenricoHenryHighlandHopewellIsle of WightJames CityKing and QueenKing GeorgeKing WilliamLancasterLeeLexingtonLoudounLouisaLunenburgLynchburgMadisonManassasManassas ParkMartinsvilleMathewsMecklenburgMiddlesexMontgomeryNelsonNew KentNewport NewsNorfolkNorthamptonNorthumberlandNortonNottowayOrangePagePatrickPetersburgPittsylvaniaPoquosonPortsmouthPowhatanPrince EdwardPrince GeorgePrince WilliamPulaskiRadfordRappahannockRichmondRichmond (city)RoanokeRoanoke (city)RockbridgeRockinghamRussellSalemScottShenandoahSmythSouthamptonSpotsylvaniaStaffordStauntonSuffolkSurrySussexTazewellVirginia BeachWarrenWashingtonWaynesboroWestmorelandWilliamsburgWinchesterWiseWytheYorkHarrisonburg data center, 1175 North Main Street · Operating · 40 MW
Power40MW reported · stated
Floor area100,000sq ft
IT load7.5MW

Who is behind it

ProjectHarrisonburg data center, 1175 North Main StreetAlso: Cyber Integration Center, DBT-Data Cyber Integration Center, former Tyco building
Developer and teamAC DataCom Digital Infrastructure Investments (owner)
DBT-Data (former owner)
End userAnthem Health

The record, newest first

  1. Owner AC DataCom Digital Infrastructure Investments secured $43.8 million in permanent financing from Valley National Bank; the building was reported as fully leased to Anthem Health since 2015. (Baxtel, Feb. 13, 2023)

  2. DBT-Data bought the facility back from Harris Corp., which had acquired it in 2010 and later exited cloud hosting. (Data Center Knowledge, Nov. 11, 2013)

  3. Criticon announced a $115 million plan to turn the former Tyco building at 1175 North Main Street into a co-location data center, adding 40,000 sq ft to a 150,000 sq ft facility. (Virginia Economic Development Partnership, March 2007)

Conflicts and open questions

  • Square footage reported as 150,000 in the 2007 plan and 100,000 in 2023; the 2023 figure is used.
  • Under 50 MW; kept because operating campuses of any size are in scope.
  • Coordinates approximate, placed on North Main Street in north Harrisonburg near the reported address.

The full record

Status note
Reported in 2023 as fully leased to Anthem Health since 2015 and refinanced by its owner.
Power note
Baxtel (2023) reports DBT-Data claimed up to 40 MW for the site after buying it in 2008; Data Center Knowledge cited 7.5 MW of conditioned IT load in 2013. Under 50 MW.
Evidence
News reports; primary records not yet obtained
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.