Data center campus · Northwest of Highway 92 and Butler Farm Road, Chase City, Mecklenburg, Virginia

Microsoft LYH campus, Chase City

Approved as of May 1, 2025

A Microsoft data center site near Chase City permitted by DEQ for backup generators serving buildings LYH03 through LYH06. Also known as: LYH03, LYH04, LYH05, LYH06.

Cite← Virginia data centers
AccomackAlbemarleAlexandriaAlleghanyAmeliaAmherstAppomattoxArlingtonAugustaBathBedfordBlandBotetourtBristolBrunswickBuchananBuckinghamBuena VistaCampbellCarolineCarrollCharles CityCharlotteCharlottesvilleChesapeakeChesterfieldClarkeColonial HeightsCovingtonCraigCulpeperCumberlandDanvilleDickensonDinwiddieEmporiaEssexFairfaxFairfax (city)Falls ChurchFauquierFloydFluvannaFranklinFranklin (city)FrederickFredericksburgGalaxGilesGloucesterGoochlandGraysonGreeneGreensvilleHalifaxHamptonHanoverHarrisonburgHenricoHenryHighlandHopewellIsle of WightJames CityKing and QueenKing GeorgeKing WilliamLancasterLeeLexingtonLoudounLouisaLunenburgLynchburgMadisonManassasManassas ParkMartinsvilleMathewsMecklenburgMiddlesexMontgomeryNelsonNew KentNewport NewsNorfolkNorthamptonNorthumberlandNortonNottowayOrangePagePatrickPetersburgPittsylvaniaPoquosonPortsmouthPowhatanPrince EdwardPrince GeorgePrince WilliamPulaskiRadfordRappahannockRichmondRichmond (city)RoanokeRoanoke (city)RockbridgeRockinghamRussellSalemScottShenandoahSmythSouthamptonSpotsylvaniaStaffordStauntonSuffolkSurrySussexTazewellVirginia BeachWarrenWashingtonWaynesboroWestmorelandWilliamsburgWinchesterWiseWytheYorkMicrosoft LYH campus, Chase City · Approved
PowerNot statedNot reported in the records found

Who is behind it

ProjectMicrosoft LYH campus, Chase CityAlso: LYH03, LYH04, LYH05, LYH06
Developer and teamMicrosoft
End userMicrosoft

The record, newest first

  1. DEQ approved a permit for 110 3,000 kW and four 500 kW backup diesel generators, listed as to be constructed, at LYH03 through LYH06. (Virginia Department of Environmental Quality, May 1, 2025)

Conflicts and open questions

  • Microsoft's LYH10 data center is a separate permit at US 58 and Ridge Road in Boydton and is left in microsoft-mecklenburg.
  • May overlap with the Chase City sites counted in microsoft-mecklenburg.

The full record

Status note
DEQ approved a permit to construct and operate; it lapses if continuous construction has not begun by Nov. 1, 2026.
Power note
Capacity not disclosed. The DEQ permit covers 114 backup generators rated 332 MW combined (sum of listed ratings), not the facility load.
Evidence
Primary public records
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.