Data center campus · 39 Commerce Drive, near Clarksville (Boydton mailing address), Mecklenburg, Virginia
Microsoft AVC17 campus, Clarksville
Approved
as of April 22, 2025
A Microsoft data center campus at 39 Commerce Drive near Clarksville whose DEQ air permit covers backup generators for buildings AVC17 through AVC21. Also known as: AVC17.
PowerNot statedNot reported in the records found
Who is behind it
The record, newest first
DEQ approved a permit for 130 3,000 kW and five 500 kW backup diesel generators serving AVC17 through AVC21. (Virginia Department of Environmental Quality, April 22, 2025)
Microsoft's application to amend the permit was dated Sept. 30, 2024. (Virginia Department of Environmental Quality, April 22, 2025)
DEQ issued the site's first air permit, later superseded. (Virginia Department of Environmental Quality, April 22, 2025)
Conflicts and open questions
- The permit gives a Boydton mailing ZIP but describes the site as Clarksville.
- The 2024 local count in microsoft-mecklenburg listed its single Clarksville site as a Peraton facility, so this campus may not be covered by that entry.
The full record
- Status note
- DEQ approved a permit to construct and operate that lapses unless continuous construction began by Oct. 22, 2026 or DEQ granted an extension; no record of either was found.
- Power note
- Capacity not disclosed. The DEQ permit covers 135 backup generators rated about 392.5 MW combined (sum of listed ratings); that is backup generation, not the IT or utility load.
- Evidence
- Primary public records
- Size class
- Under 50 MW (outside main scope; kept for completeness)