Data center campus · Middletown, Frederick, Virginia

Middletown Data Center

Operating as of Aug. 2023

A hardened 1970s facility on Valley Pike, renovated with its own natural-gas microgrid and marketed to tenants with about 33,000 sq ft of white space and 6.7 MW of IT capacity. Also known as: MDC.

Cite← Virginia data centers
AccomackAlbemarleAlexandriaAlleghanyAmeliaAmherstAppomattoxArlingtonAugustaBathBedfordBlandBotetourtBristolBrunswickBuchananBuckinghamBuena VistaCampbellCarolineCarrollCharles CityCharlotteCharlottesvilleChesapeakeChesterfieldClarkeColonial HeightsCovingtonCraigCulpeperCumberlandDanvilleDickensonDinwiddieEmporiaEssexFairfaxFairfax (city)Falls ChurchFauquierFloydFluvannaFranklinFranklin (city)FrederickFredericksburgGalaxGilesGloucesterGoochlandGraysonGreeneGreensvilleHalifaxHamptonHanoverHarrisonburgHenricoHenryHighlandHopewellIsle of WightJames CityKing and QueenKing GeorgeKing WilliamLancasterLeeLexingtonLoudounLouisaLunenburgLynchburgMadisonManassasManassas ParkMartinsvilleMathewsMecklenburgMiddlesexMontgomeryNelsonNew KentNewport NewsNorfolkNorthamptonNorthumberlandNortonNottowayOrangePagePatrickPetersburgPittsylvaniaPoquosonPortsmouthPowhatanPrince EdwardPrince GeorgePrince WilliamPulaskiRadfordRappahannockRichmondRichmond (city)RoanokeRoanoke (city)RockbridgeRockinghamRussellSalemScottShenandoahSmythSouthamptonSpotsylvaniaStaffordStauntonSuffolkSurrySussexTazewellVirginia BeachWarrenWashingtonWaynesboroWestmorelandWilliamsburgWinchesterWiseWytheYorkMiddletown Data Center · Operating
PowerNot statedNot reported in the records found
Floor area33,000sq ft
IT load6.7MW

Who is behind it

ProjectMiddletown Data CenterAlso: MDC
Developer and teamMiddletown Data Center
Cardinal Energy Corp.
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. The operator said the renovated facility was fully commissioned and open to tenants. It offers about 33,000 sq ft of white space and 6.7 MW of IT capacity, with power from an on-site natural-gas microgrid. (Middletown Data Center, Aug. 11, 2023; DatacenterDynamics, Aug. 2023)

Conflicts and open questions

  • Under 50 MW. Kept as an operating site.
  • DCD gives the address as 8209 Valley Pike and names Cardinal Energy Corp. as owner. DCD says the building opened in the early 1970s as a hardened financial-processing site and later served as an AT&T microwave station and an Experis data center.
  • The release date comes from the PDF filename on the operator's media page (August 11, 2023). The DCD article shows no date.
  • Coordinates are approximate, placed from the reported Valley Pike address in Middletown.

The full record

Status note
The operator announced the renovated facility as fully commissioned and ready for tenants.
Power note
The operator advertises 6.7 MW of IT capacity, so the site is under 50 MW. Total utility load is not stated.
Evidence
Primary public records
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.