Data center campus · Cleveland, Russell, Virginia
Oasis Moss No. 3 data center site
Proposed
as of Sept. 15, 2026
Oasis Digital Properties holds an option on 236 acres of the former Moss No. 3 coal mine near Cleveland for three or four data center buildings.
PowerNot statedNot reported in the records found
Site236acres
Who is behind it
ProjectOasis Moss No. 3 data center site
Developer and teamOasis Digital Properties
Russell County Industrial Development Authority (through landowner)
Russell County Industrial Development Authority (through landowner)
End userNot found in the recordsNot yet named in any record or credited report we have found.
The record, newest first
Oasis described three or four buildings on 236 acres off Gravel Lick Road and said it was still seeking tenants. (Cardinal News, Sept. 15, 2026)
Oasis signed a contract with the county industrial development authority in spring 2025 giving it an option to buy the land. (Cardinal News, Sept. 15, 2026)
Conflicts and open questions
- Coordinates approximate, near the town of Cleveland.
The full record
- Status note
- Developer holds an option on the industrial development authority's land, is seeking tenants and says it is working with DEQ; no construction.
- Power note
- Appalachian Power reportedly confirmed it could supply 300 MW from the Clinch River Plant, first 100 MW by 2028 if a deal is final; not a project rating.
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)