OVHcloud Vint Hill data center
OVHcloud's first U.S. data center, set up in 2016 in an existing building at Vint Hill Business Park and still operating in 2026. Also known as: OVH Vint Hill, VIN1.
Who is behind it
The record, newest first
OVHcloud US marked 10 years in the U.S. and said it operates data centers in Vint Hill and Hillsboro, Oregon. (StorageNewsletter, Aug. 31, 2026)
OVH described Vint Hill as the site of its first U.S. data center and one of its two U.S. headquarters. (OVHcloud US, Aug. 1, 2017)
OVH bought an 8.6-acre property at 6872 Watson Court for $4.8 million. Its main 84,200 sq ft building was to hold the data center. (Fauquier Now, Oct. 2016)
The governor's office announced that OVH would invest $47 million and create 54 jobs. The company planned its North American headquarters and first U.S. data center in an existing building at Vint Hill. (Virginia Economic Development Partnership, Oct. 6, 2016)
Conflicts and open questions
- Operating campus. MW not reported and probably small, but no figure was found, so it is not labeled under 50 MW.
- The Fauquier Now article shows no date. Its content puts it in late 2016.
- Coordinates are approximate, placed from the reported Watson Court address at Vint Hill.
The full record
- Status note
- OVHcloud's 10-year anniversary release in August 2026 says it operates data centers in Vint Hill and in Hillsboro, Oregon.
- Power note
- No power figure in any source opened.
- Evidence
- Primary public records
- Size class
- Under 50 MW (outside main scope; kept for completeness)