Data center campus · eastern Wythe County near the Pulaski line, Wythe, Virginia

TAC Data Centers Wythe County campus

Proposed as of June 4, 2026

TAC Data Centers plans a gigawatt-plus campus of nine to 11 buildings on about 1,000 acres southeast of I-81 in eastern Wythe County, with the first half online in 2029.

Cite← Virginia data centers
AccomackAlbemarleAlexandriaAlleghanyAmeliaAmherstAppomattoxArlingtonAugustaBathBedfordBlandBotetourtBristolBrunswickBuchananBuckinghamBuena VistaCampbellCarolineCarrollCharles CityCharlotteCharlottesvilleChesapeakeChesterfieldClarkeColonial HeightsCovingtonCraigCulpeperCumberlandDanvilleDickensonDinwiddieEmporiaEssexFairfaxFairfax (city)Falls ChurchFauquierFloydFluvannaFranklinFranklin (city)FrederickFredericksburgGalaxGilesGloucesterGoochlandGraysonGreeneGreensvilleHalifaxHamptonHanoverHarrisonburgHenricoHenryHighlandHopewellIsle of WightJames CityKing and QueenKing GeorgeKing WilliamLancasterLeeLexingtonLoudounLouisaLunenburgLynchburgMadisonManassasManassas ParkMartinsvilleMathewsMecklenburgMiddlesexMontgomeryNelsonNew KentNewport NewsNorfolkNorthamptonNorthumberlandNortonNottowayOrangePagePatrickPetersburgPittsylvaniaPoquosonPortsmouthPowhatanPrince EdwardPrince GeorgePrince WilliamPulaskiRadfordRappahannockRichmondRichmond (city)RoanokeRoanoke (city)RockbridgeRockinghamRussellSalemScottShenandoahSmythSouthamptonSpotsylvaniaStaffordStauntonSuffolkSurrySussexTazewellVirginia BeachWarrenWashingtonWaynesboroWestmorelandWilliamsburgWinchesterWiseWytheYorkTAC Data Centers Wythe County campus · Proposed · 1,000 MW
Power1,000MW reported · stated
Floor area4,000,000sq ft
Site1,000acres

Who is behind it

ProjectTAC Data Centers Wythe County campus
Developer and teamTAC Data Centers (The Ardent Companies)
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. The developer outlined about 1,000 acres, 3.5 to 4 million sq ft in nine to 11 buildings and more than 1 GW served by Appalachian Power, with phases due 2029 and 2031-32. (Cardinal News, June 4, 2026)

Conflicts and open questions

  • Square footage reported as 3.5 to 4 million; the upper figure is used.
  • Coordinates approximate, about 10 miles east of Wytheville southeast of I-81.

The full record

Status note
No rezoning needed because the county has no zoning; building, DEQ and air permits are still required.
Power note
Developer said more than 1 GW.
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.