Data center campus · 8805 N. Reems Rd., Glendale, Maricopa County, Arizona

Aligned Data Centers Glendale (PHX-13 campus)

Under construction as of April 15, 2025

Aligned is building the first of four planned data centers on a 100-acre campus in west Glendale. APS is supplying a new 230 kV transmission line. Also known as: Aligned PHX-13.

Cite← Arizona data centers
Apache CountyCochise CountyCoconino CountyGila CountyGraham CountyGreenlee CountyLa Paz CountyMaricopa CountyMohave CountyNavajo CountyPima CountyPinal CountySanta Cruz CountyYavapai CountyYuma CountyAligned Data Centers Glendale (PHX-13 campus) · Under construction
PowerNot statedNot reported in the records found
Site100acres

Who is behind it

ProjectAligned Data Centers Glendale (PHX-13 campus)Also: Aligned PHX-13
Developer and teamAligned Data Centers
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. Aligned broke ground on PHX-13, a 72 MW building and the first of four planned on the 100-acre Glendale site. APS will deliver a new 230 kV line. (City of Glendale, April 17, 2025; Independent Newsmedia (YourValley.net), April 17, 2025; KTAR News, April 18, 2025)

Conflicts and open questions

  • The Real Deal (May 2026) refers to an Aligned project in Glendale near Luke Air Force Base. This is presumably the same site.
  • The lead's building names (PHX-07, -12, -13, -14) are not confirmed except PHX-13.

The full record

Status note
Groundbreaking for PHX-13, the first of four planned buildings, took place on April 15, 2025.
Power note
72 MW is stated for PHX-13 only, the first of four buildings. No campus total has been published.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.