Data center campus · 1301 W University Dr, Mesa, Maricopa County, Arizona
Centersquare PHX3
Operating
as of Nov. 1, 2026
A colocation data center in west Mesa that Centersquare markets as part of its Phoenix region.
Power17.3MW reported · stated
Floor area50,256sq ft
Who is behind it
ProjectCentersquare PHX3
Developer and teamCentersquare (Csquare)
End userNot found in the recordsNot yet named in any record or credited report we have found.
The record, newest first
Centersquare's Phoenix spec sheet lists PHX3 at 1301 W University Dr in Mesa with 50,256 sq ft and 17.3 MW of utility power. (Centersquare (Csquare), Nov. 1, 2026; Centersquare (Csquare), Nov. 1, 2026)
Conflicts and open questions
- Operator page does not give an explicit status; treated as operating because space is offered for immediate reservation.
- Not the same as the tracked Mesa hyperscale campuses.
The full record
- Status note
- Marketed with colocation space and power available.
- Power note
- Spec sheet: 17.3 MW utility power, 8 MW UPS, 11.5 MW generator for PHX3.
- Evidence
- Primary public records
- Size class
- Under 50 MW (outside main scope; kept for completeness)