Data center campus · 8811 E. Warner Road, Mesa, Maricopa County, Arizona
Edged Phoenix (PHX01-1)
Operating
as of April 2026
Edged's two-story, 36 MW waterless-cooled data center on Warner Road in Mesa. Also known as: Edged Energy Phoenix.
Power36MW reported · stated
Floor area210,000sq ft
Site12acres
Who is behind it
ProjectEdged Phoenix (PHX01-1)Also: Edged Energy Phoenix
Developer and teamEdged (through Endeavour)
End userNot found in the recordsNot yet named in any record or credited report we have found.
The record, newest first
Edged announced the Mesa facility had opened. (IT Brief US, April 7, 2026; DatacenterDynamics, April 2026)
Edged broke ground on a 210,000 sq ft, 36 MW facility on 12 acres; Haydon is the builder and SRP the power provider. (DatacenterDynamics, Aug. 16, 2024)
Conflicts and open questions
- Edged is part of Endeavour; not related to EdgeConneX despite the commercial lead bundling them.
- Operator's own page not read; evidence kept as reported.
The full record
- Evidence
- News reports; primary records not yet obtained
- Size class
- Under 50 MW (outside main scope; kept for completeness)